FAQ
Construction Finance Questions, Answered
Every answer is sourced from US federal regulations and Washington State law. No guessworkβjust verified information.
AIA Billing & Progress Payments
The AIA G702 serves as the Application and Certificate for Payment, summarizing the contract sum, changes, and amount due, while the G703 serves as the Continuation Sheet, providing a detailed breakdown of costs based on the Schedule of Values. Together, they provide a standardized format for architects and owners to verify progress against the contract. (Source: AIA Document G702-1992 Instructions, Summary of Application and Certificate for Payment)
The AIA G702 serves as a summary document where the contractor certifies that the work described in the accompanying G703 is complete. It includes the original contract sum, net change orders, total completed and stored to date, retainage amounts, and the remaining balance to finish. (Source: AIA Document G702-1992, Instructions)
The Schedule of Values must break down the entire contract sum into specific line items or portions of work, such as labor and materials for specific trades. This breakdown is used as the basis for reviewing the contractor's periodic applications for payment. (Source: FASB ASC 606, Revenue from Contracts with Customers)
The Schedule of Values must be broken down into specific line items that represent the entire contract sum, typically using CSI MasterFormat divisions, to allow the architect to determine the percentage of completion for each work item. This breakdown must be submitted and approved by the architect prior to the first application for payment. (Source: FASB ASC 606 / AIA A201 General Conditions, Section 9.2)
For public improvement contracts, public bodies must reserve a contract retainage not to exceed five percent of the moneys earned by the contractor. This sum is held as a trust fund for the protection and payment of laborers, subcontractors, and state taxes. (Source: Revised Code of Washington, RCW 60.28.011(1)(a))
For public improvement contracts, public bodies must reserve a contract retainage not to exceed five percent of the moneys earned by the contractor, which is held as a trust fund for the protection of laborers and the state. (Source: Revised Code of Washington, RCW 60.28.011(1)(a))
Yes, Washington law recognizes electronic records and signatures as having the same legal effect as physical signatures, provided they meet the standards for authenticity and intent under the Uniform Electronic Transactions Act. (Source: Revised Code of Washington, RCW 1.80.060)
Yes, Washington law stipulates that a record or signature may not be denied legal effect or enforceability solely because it is in electronic form. This applies to construction contracts and payment applications provided they meet security and attribution standards. (Source: Revised Code of Washington, RCW 1.80.060)
General contractors must pay their subcontractors for satisfactory performance within ten days of receipt of each progress payment from the state or any county, city, or town. (Source: Revised Code of Washington, RCW 39.04.250)
On public works projects exceeding $20,000, the contractor may request that the retained funds be placed in an interest-bearing account, with all interest earned belonging to the contractor. (Source: Revised Code of Washington, RCW 60.28.011(4)(b))
Yes, if payment is not made within thirty days of a proper pay request, the unpaid amount shall bear interest at the rate of one percent per month or fraction thereof until paid. (Source: Revised Code of Washington, RCW 39.76.011)
If a prime contractor receives payment from an owner, they must pay their subcontractors for satisfactory performance no later than ten days after receiving the payment. Failures may result in interest penalties. (Source: Revised Code of Washington, RCW 39.04.250)
Column F is used to account for the value of materials and equipment that have been purchased and are stored on-site or at an approved off-site location, but have not yet been incorporated into the work. (Source: AIA Document G703-1992, Instructions)
The 'Materials Presently Stored' column typically includes the value of materials and equipment suitably stored on-site or at an agreed-upon off-site location for which payment is sought, though they are not yet incorporated into the work. (Source: AIA Document G703-1992 Instructions, Column F)
Retainage must be released within 60 days of completion of all contract work, provided that the public body has received certificates of release from the Department of Revenue, Department of Labor and Industries, and Employment Security Department. (Source: Revised Code of Washington, RCW 60.28.011)
Retainage must be released within 60 days of final acceptance of the project, provided that all necessary releases from the Department of Revenue, Employment Security Department, and Department of Labor and Industries are obtained. (Source: Revised Code of Washington, RCW 60.28.011)
The standard AIA G702 form includes a section for the Architect's certification and many owners require it to be notarized to verify the contractor's signature; however, the requirement specifically depends on the terms of the signed owner-contractor agreement. (Source: AIA Document G702-1992, Contractor's Affidavit)
In most private contracts, if an owner fails to make a progress payment without cause, the contractor may be entitled to interest at the rate of one percent per month or the rate specified in the contract, whichever is higher. (Source: Revised Code of Washington, RCW 39.76.011)
Yes, a contractor may provide a retainage bond for all or any portion of the contract retainage in a form acceptable to the public body and from an authorized surety company. (Source: Revised Code of Washington, RCW 60.28.011(6))
An owner may withhold payment for a portion of a progress payment that is in dispute, but must pay the undisputed portion in a timely manner as required by the contract and state law. (Source: Revised Code of Washington, RCW 60.04.221)
Yes, the standard AIA G702 format includes a section for a Notary Public's signature and seal, certifying that the contractor's representative signed the document under oath and that the work is complete as stated. (Source: AIA Document G702-1992, Instructions)
Under ASC 606, revenue for construction contracts is generally recognized over time as performance obligations are satisfied, often using an input method such as 'costs incurred to total estimated costs' to measure progress. (Source: FASB Accounting Standards Codification, ASC 606-10-25-27)
Change orders are summarized on the G702 and specifically listed as individual line items on the G703 Schedule of Values once they have been formally approved in writing by the owner and architect. (Source: AIA Document G202-1992, Instructions)
If an owner fails to make a required payment within the timeframes specified by contract, the contractor may, after providing 10 days' written notice, stop work until the payment is received. (Source: Revised Code of Washington, RCW 60.04.221)
Change orders should be summarized on the G702 summary page and detailed as separate line items on the G703 Continuation Sheet, adjusted in the 'Scheduled Value' column only after they have been formally executed. (Source: AIA Document G201-2017 / AIA G702 Instructions)
To receive payment for stored materials, the contractor must often provide evidence that the materials are insured and stored in a secure location, and in some cases, the architect must physically verify the inventory. (Source: AIA Document A201-2017, Section 9.3.2)
A progress billing is considered satisfactory when it is submitted on the proper forms (like AIA G702/703) with all required certifications, lien waivers, and supporting documentation as specified in the contract. (Source: Revised Code of Washington, RCW 39.04.250)
Percent complete is calculated by dividing the sum of 'Total Completed and Stored to Date' (Column G) by the 'Scheduled Value' (Column C) for each line item. (Source: AIA Document G703-1992, Instructions)
Bonding & Insurance
To be registered as a general contractor in Washington, you must file a surety bond with the Department of Labor and Industries in the amount of $12,000. This bond is primarily for the protection of persons who perform labor, provide materials, or have a breach of contract claim against the contractor. (Source: Revised Code of Washington, RCW 18.27.040(1))
Specialty contractors are required to maintain a surety bond in the amount of $6,000. The bond must be issued by a surety company authorized to do business in the state of Washington and is a prerequisite for legal operation. (Source: Revised Code of Washington, RCW 18.27.040(1))
Washington law requires performance and payment bonds for all public works contracts with the state, county, municipality, or other public body. For contracts exceeding $150,000, a bond for the full contract price is mandatory to ensure the completion of the work and payment of all laborers and suppliers. (Source: Revised Code of Washington, RCW 39.08.010)
Yes, a contractor may file with the department a cash deposit or other negotiable security instead of a surety bond. This deposit is held by the department to satisfy the same claims and obligations as a standard surety bond. (Source: Revised Code of Washington, RCW 18.27.040(6))
Surety companies typically require financial statements prepared in accordance with GAAP to assess a contractor's prequalification. Under ASC 606, contractors must recognize revenue from contracts with customers based on the transfer of control, which significantly impacts the balance sheet and bonding capacity. (Source: FASB Accounting Standards Codification, ASC 606)
Insurance premiums, including Builders Risk, that are ordinary and necessary expenses of carrying on a trade or business are generally deductible. However, if the insurance relates to the construction of a self-produced asset, costs may need to be capitalized under the Uniform Capitalization (UNICAP) rules. (Source: Internal Revenue Code, 26 USC Β§ 263A)
The Miller Act requires a prime contractor on federal construction contracts exceeding $100,000 to post both a performance bond for the protection of the government and a payment bond for the protection of subcontractors and material suppliers. (Source: United States Code, 40 USC Β§ 3131)
Yes, to register as a contractor in Washington, an applicant must provide evidence of public liability and property damage insurance. The minimum limits required are $20,000 for property damage and $50,000 for injury or death to one person (or $100,000 for more than one person). (Source: Revised Code of Washington, RCW 18.27.050)
General Liability covers bodily injury and property damage, while Professional Liability (Errors & Omissions) covers financial losses resulting from professional negligence, such as design errors. Standard AIA contracts often specify that design-build contractors must maintain professional liability insurance. (Source: AIA Document A201-2017, Section 11.1)
The cost of performance and payment bonds is typically classified as a direct job cost and recognized in the period it is incurred or over the life of the contract. Under GAAP, these costs are part of the total estimated contract costs used to calculate the percentage of completion. (Source: FASB Accounting Standards Codification, ASC 606-10-25-27)
Action upon a contractor's bond must be commenced by filing a complaint in superior court within one year from the date the claimed labor was performed and assistance rendered or materials and equipment furnished. (Source: Revised Code of Washington, RCW 18.27.040(3))
Virtually all employers in Washington must provide industrial insurance (Workers' Comp) coverage for their employees. This is managed through the state fund, and failure to maintain coverage can lead to the suspension of the contractor's registration. (Source: Revised Code of Washington, RCW 51.12.020)
When a loss occurs, insurance proceeds should be recognized as a gain in the period the recovery becomes probable. This gain is typically offset against the recognized loss of the asset or the cost of repairs incurred to date. (Source: FASB Accounting Standards Codification, ASC 450-30)
Washington's version of the federal Miller Act, found in RCW 39.08, requires contractors on public works to provide a bond to protect against non-payment of subcontractors and suppliers. For projects under $150,000, the public entity may allow the contractor to retain 10% of the contract amount in lieu of a bond. (Source: Revised Code of Washington, RCW 39.08.010)
Washington contractors typically need three types: a license bond (required for contractor registration under RCW 18.27), a bid bond (5-10% of bid amount for public works), and performance/payment bonds (required on public works over $150,000 under RCW 39.08). The license bond amount is $12,000 for general contractors and $6,000 for specialty contractors.
Surety bond premiums typically range from 1-3% of the contract amount. The rate depends on the contractor's financial strength, credit history, work experience, and project complexity. Premiums are usually calculated on a sliding scaleβhigher percentages for the first $100K, lower for amounts above. The premium is a tax-deductible business expense.
SDI is an alternative to traditional surety bonds where the general contractor self-insures against subcontractor default. The GC pays premiums to an insurer and manages subcontractor risk directly. SDI typically covers the cost to complete work, correct defective work, and recover delay damages. It is most common on large commercial projects.
All Washington construction employers must carry workers' compensation through the Washington State Fund (administered by L&I) unless they qualify as a self-insurer. There is no option for private insurance in Washington (it is a monopolistic state fund). Premiums are based on classification codes, payroll amounts, and experience modification rates.
Yes. The SBA's Surety Bond Guarantee Program helps small and emerging contractors who cannot obtain bonds through regular channels. The SBA guarantees 80-90% of the bond, reducing the surety's risk. Eligible contracts must not exceed $6.5 million ($10 million for federal contracts). Contractors apply through an SBA-approved surety company.
Builder's risk insurance covers property damage to a structure under construction, including materials, fixtures, and equipment. It typically covers perils like fire, wind, theft, and vandalism. Coverage begins at project start and ends at substantial completion or occupancy. It does not cover general liability, workers' comp, or damage from faulty workmanship.
An OCIP, or "wrap-up" policy, is a consolidated insurance program purchased by the property owner that covers all contractors on a project. It typically includes general liability, workers' comp, and excess liability. Contractors must remove their own insurance costs from bids when enrolled in an OCIP. Common on projects exceeding $50 million.
The EMR compares a contractor's actual workers' comp claims to expected claims for their industry. An EMR of 1.0 is average; below 1.0 means fewer claims (lower premiums), above 1.0 means more claims (higher premiums). A high EMR can also disqualify contractors from bidding on certain projects. In Washington, EMR is calculated by L&I.
While not legally required, most general contractors and project owners require subcontractors to carry umbrella/excess liability coverage of $1-5 million. This coverage sits above the primary general liability and auto liability policies. It is essential for contractors working on commercial, multi-family, or public works projects.
An occurrence policy covers claims for incidents that happen during the policy period, regardless of when the claim is filed. A claims-made policy only covers claims filed during the policy period. Occurrence policies are standard for construction general liability because construction defects may not be discovered for years after completion.
To obtain a performance bond for public works projects, contractors must: (1) demonstrate financial stability through CPA-prepared financial statements, (2) provide a strong work history and project references, (3) maintain good personal credit (typically 680+), (4) show adequate working capital (usually 10% of bond amount), and (5) apply through a surety company or bond agent. The Miller Act (40 USC Β§3131) requires performance bonds on federal projects over $150,000, and most states have similar requirements. A construction bookkeeper like Scaffold Bookkeeping can prepare the financial documentation sureties require. (Source: 40 USC Β§3131, Miller Act)
Surety companies typically want a current ratio (current assets Γ· current liabilities) of 1.3 to 2.0. Below 1.3 signals liquidity risk that may limit your bonding capacity (Source: 40 USC Β§3131, Miller Act).
Surety companies give higher bond limits to well-structured entities. C-Corps with retained earnings get the highest limits. S-Corps and LLCs with clean financials and strong working capital can qualify for $1M-$10M+ bond programs (Source: 40 USC Β§3131, Miller Act).
Bonding & Insurance Accounting
A loss run report is an official document provided by an insurer that outlines the claims history of a policyholder during a specific period. For contractors, these reports are vital because they serve as 'credit scores' for insurance; bonding companies and underwriters use them to evaluate risk, determine premiums, and assess the contractor's safety management effectiveness. (Source: RCW 48.18.545, Section 1)
To maintain registration in Washington, contractors must provide a surety bond in the amount of $12,000 for general contractors or $6,000 for specialty contractors. Financially, this bond serves as a guarantee for wages, taxes, and liquidated damages, and must be issued by a surety insurer authorized by the Insurance Commissioner. (Source: RCW 18.27.040, Section 1)
Surety bond premiums are typically paid in advance and should be recorded as a prepaid expense (asset) on the balance sheet. These costs are then amortized to the specific construction project's costs over the duration of the performance period as the obligation is satisfied. (Source: FASB ASC 606-10-25-17; FASB ASC 340-40)
Surety companies primarily evaluate a contractorβs 'working capital' (current assets minus current liabilities) and 'net worth' to determine bonding limits. They typically look for a debt-to-equity ratio that demonstrates financial stability and the ability to cover potential losses. (Source: Washington State Department of Transportation, Construction Manual Section 1-02.1)
In Washington, a contractor's EMR (Experience Factor) directly impacts bidding eligibility for public works. Under state law, a contractor may be disqualified from bidding if they have been found to be a 'non-responsible' bidder due to a safety track record that exceeds specific industrial insurance benchmarks. An EMR above 1.0 indicates a higher-than-average risk, which many public and private owners use as a threshold to pre-exclude contractors from the bidding process to mitigate workplace safety liabilities. (Source: RCW 39.04.350, Section 1(e))
Completed Operations insurance covers liability for property damage or injuries that occur after a construction project is finished. Under Washington law, this is a distinct component of General Liability coverage that protects against 'construction defect' claims. From an accounting perspective, these premiums are typically treated as an indirect job cost or administrative expense, provided the coverage meets the state's requirements for commercial liability. (Source: RCW 48.18.140, Section 1)
In Washington, the Department of Labor & Industries calculates an 'experience factor' based on a contractor's actual claim costs compared to average expected costs. An experience factor below 1.00 indicates a safer track record and results in lower premiums, while a factor above 1.00 increases workers' compensation costs. (Source: WAC 296-17-850, Section 1)
Surety companies typically require a complete financial file to assess prequalification, which includes a balance sheet, an income statement, and a statement of cash flows. Crucially for construction, they require a 'Work in Progress' (WIP) schedule (Schedule of Contracts) that reconciles to the financial statements. Washington state law requires certain contractors to maintain specific levels of financial responsibility, and sureties use these audited or reviewed statements to ensure the contractor meets the net worth and working capital requirements necessary to back the bond. (Source: WAC 296-200A-030, Section 4)
A deductible reduces the limit of insurance available and is usually paid by the insurer then reimbursed by the contractor, whereas a Self-Insured Retention (SIR) must be paid by the contractor before the insurance policy is even triggered. For accounting, contractors must accrue a liability for unpaid claims within the SIR layer if the loss is probable and estimable. (Source: FASB ASC 450-20; WA WAC 284-24-065)
Contractors must maintain and provide records including payroll journals, individual earnings records, and federal tax forms (941). For construction specifically, records must clearly distinguish between different risk classifications to ensure correct premium assessment. (Source: Revised Code of Washington, RCW 51.48.030)
Excess liability insurance provides additional coverage limits specifically over a single underlying policy (such as General Liability), whereas Umbrella insurance provides higher limits over several underlying policies and may cover gaps or 'drop down' for risks not covered by primary policies. Both are used by contractors to meet the high limit requirements of large-scale construction contracts. (Source: WAC 284-30-330, Section 1)
Subcontractor Default Insurance (SDI) premiums are generally treated as deductible ordinary and necessary business expenses under federal tax law. For accounting purposes, these costs are typically allocated to specific project costs rather than general overhead. Under IRS regulations, insurance premiums paid or incurred during the taxable year are deductible if they are directly connected with the taxpayer's trade or business, provided they do not represent a reserve for self-insurance. (Source: 26 U.S. Code Β§ 162, Section (a))
Yes. To avoid secondary liability for unpaid premiums, a prime contractor must verify that a subcontractor has a valid certificate of coverage and an active account with the Department of Labor and Industries at the time of the subcontract. (Source: Revised Code of Washington, RCW 51.12.070)
Under federal law for public works (The Miller Act), a performance bond protects the government by guaranteeing the completion of the contract according to its terms, whereas a payment bond is specifically for the protection of all persons supplying labor and material in carrying out the work provided for in the contract. (Source: 40 U.S.C. Β§ 3131, Section b)
In Washington, workers' compensation is managed via a state fund. A contractor can appeal their experience rating or classification by filing a written protest with the Department of Labor & Industries (L&I). If the Department's decision is unsatisfactory, the employer may file a further appeal with the Board of Industrial Insurance Appeals (BIIA) within 60 days of the decision. (Source: RCW 51.52.050; RCW 51.52.060)
Buildertrend Setup
Yes, Buildertrend syncs bills, invoices, and payments to both QuickBooks Desktop and Online. Costs are mapped to the correct customer/job and expense accounts based on your cost code configuration. Verify that your Buildertrend cost codes map to the correct QuickBooks accounts before enabling the sync.
Cash Flow & AR/AP
Contractors should provide a Notice to Owner or Preliminary Notice to preserve their right to file a mechanic's lien if payment is not received. This documentation ensures that any person furnishing labor, professional services, materials, or equipment for the improvement of real property has a lien upon the improvement for the contract price. (Source: Revised Code of Washington, RCW 60.04.021)
On public improvement contracts, public bodies must reserve a contract retainage not to exceed five percent of the moneys earned by the contractor. This sum is held as a trust fund for the protection and payment of any person or persons who shall perform labor or furnish supplies and for the payment of taxes due to the state. (Source: Revised Code of Washington, RCW 60.28.011)
The timing gap between paying for labor and materials upfront and receiving payment from clients 30-90+ days later is the primary cash flow challenge. This is compounded by retainage holdbacks (typically 5-10%), slow change order approvals, and seasonal work fluctuations. Effective progress billing and AR management are critical mitigations. (Source: CFMA Financial Survey of the Construction Industry)
Review the AR aging report weekly, categorizing invoices into current, 30, 60, 90, and 120+ day buckets. Follow up on invoices at 15 days, send formal demand letters at 60 days, and consider lien rights before deadlines expire. For retainage, track release dates tied to substantial completion and final acceptance milestones. (Source: CFMA Best Practices)
Contractors must recognize revenue over time (formerly known as the percentage-of-completion method) if the entityβs performance creates an asset that the customer controls or if the performance creates an asset with no alternative use and there is an enforceable right to payment. This aligns cash flow tracking with the transfer of control. (Source: FASB ASC, 606-10-25-27)
When a contractor receives any payment from an owner, they must pay each of their subcontractors and material suppliers out of the amount paid for the labor and materials performed or furnished by the subcontractor. This must be done within ten days of receipt of payment, unless otherwise agreed in writing. (Source: Revised Code of Washington, RCW 39.04.250)
Key practices include: (1) Match invoices to purchase orders and delivery receipts (3-way match), (2) Track subcontractor retainage payable separately, (3) Collect lien waivers before releasing payment, (4) Take advantage of early payment discounts (e.g., 2/10 net 30), (5) Schedule payments to align with project billing cycles to preserve cash flow. (Source: CFMA, Construction Financial Management)
State agencies or local governments must pay interest at a rate of one percent per month on amounts due to a contractor if the payment is not made within thirty days of receipt of a proper invoice. This protects contractor cash flow against agency administrative delays. (Source: Revised Code of Washington, RCW 39.76.011)
Under RCW 39.76, public agencies must pay contractors within 30 days of acceptance of work. Prime contractors must pay subcontractors within 10 days of receiving payment (RCW 39.04.250). Late payments accrue interest at 1% per month. Private projects follow contract terms but are subject to lien rights as leverage for timely payment. (Source: WA State Legislature, RCW 39.76, RCW 39.04.250)
Under the Tax Cuts and Jobs Act, construction businesses with average annual gross receipts of $25 million or less (adjusted for inflation) for the three prior tax years are generally permitted to use the cash method of accounting. This allows them to defer tax payments until cash is actually collected from AR. (Source: Internal Revenue Code, 26 USC Β§ 448(c))
A cash flow projection forecasts expected cash inflows (progress billings, retainage releases) and outflows (payroll, materials, subs, overhead) over a future period, typically 13 weeks. Build it by listing all active projects, their billing schedules, expected payment dates, and committed costs. Update weekly and compare actual vs. projected to catch shortfalls early. (Source: CFMA, Cash Flow Management Guide)
Document the dispute in writing immediately, specifying the contested amount and reason. Under Washington law (RCW 39.76.040), the undisputed portion of an invoice must still be paid on time. Track disputed amounts separately in your accounting system and resolve through negotiation, mediation, or contractual dispute resolution procedures. (Source: WA State Legislature, RCW 39.76.040)
The contractor must submit to the architect a schedule of values allocated to various portions of the work before the first Application for Payment. This schedule, once approved, serves as the basis for reviewing the contractor's applications for payment and ensures progress billing accurately reflects work completed. (Source: AIA Document A201-2017, Section 9.2)
Retainage (typically 5% of each progress payment) creates a cumulative cash gap that grows throughout a project. On a $1M contract, $50,000 is withheld until project completion β which could be 12-18 months. Washington law (RCW 60.28) allows contractors to request retainage be placed in interest-bearing escrow or substitute a retainage bond to improve cash flow. (Source: WA State Legislature, RCW 60.28)
If a party has made a payment request and the other party fails to pay within ten days, interest may be charged at the rate of one and one-half percent per month. Additionally, in any action to collect, the prevailing party is entitled to reasonable attorneys' fees and costs. (Source: Revised Code of Washington, RCW 39.04.250)
Strategies include: (1) Bill promptly on schedule β don't wait until month-end, (2) Send preliminary lien notices to protect lien rights, (3) Require signed lien waivers from subs before releasing their pay, (4) Offer early payment discounts, (5) Use electronic payments and online portals, (6) Escalate aged receivables at defined thresholds (30, 60, 90 days). (Source: CFMA Best Practices)
Under the completed contract method, all income and expenses related to a contract are deferred until the tax year in which the contract is completed. This is generally available only to 'home construction contracts' or small contractors who meet the gross receipts test. (Source: Internal Revenue Code, 26 USC Β§ 460(e))
Standard industry contracts allow a contractor to stop work if the architect does not issue a Certificate for Payment or if the owner fails to pay within seven days after the date established in the contract, provided the contractor gives seven additional days' written notice. (Source: AIA Document A201-2017, Section 9.7)
For contracts of $150,000 or less, at the option of the contractor or the general contractor, the public body may, in lieu of a payment and performance bond, retain ten percent of the contract amount for a period of thirty days after date of final acceptance. (Source: Revised Code of Washington, RCW 39.08.010)
A contractor may submit a bond for all or any portion of the contract retainage in a form acceptable to the public body. This allows the contractor to receive the retained funds immediately instead of waiting for project completion and closeout. (Source: Revised Code of Washington, RCW 60.28.011(6))
Costs incurred to fulfill a contract, such as mobilization, are recognized as an asset if they relate directly to a contract, generate resources that will be used in satisfying performance obligations in the future, and are expected to be recovered. (Source: FASB ASC, 340-40-25-1)
A claim of lien must be recorded not later than ninety days after the period of labor, professional services, materials, or equipment furnished by the lien claimant has ceased. This timeframe is strictly enforced for protecting accounts receivable. (Source: Revised Code of Washington, RCW 60.04.091)
On $3M in annual billings with 10% retainage, $300,000 of earned revenue is locked up until project completion. This forces contractors to use lines of credit or delay vendor payments to bridge the gap. Washington State limits public works retainage to 5% (Source: RCW 60.28.011).
The average construction company waits 83 days for payment, compared to 40 days in other industries. Long payment chains, documentation requirements, and retainage accumulation are the primary causes.
A 13-week rolling forecast projects beginning cash, expected inflows (progress billings, retainage releases), and expected outflows (payroll, materials, sub payments) week by week for 90 days. It is updated weekly to always look three months ahead, identifying cash gaps before they become emergencies.
Contractors can protect their cash flow by recording a claim of lien for labor, professional services, materials, or equipment supplied. This notice of claim of lien must be filed for recording no later than ninety days after the period of labor or services has ceased or the last materials were furnished. (Source: RCW 60.04.091)
In Washington, when a general contractor receives payment from an owner, they must pay their subcontractors for satisfactory performance no later than ten days after receipt of the funds. If payment is delayed, the subcontractor may be entitled to interest at the rate of one percent per month on the unpaid balance. (Source: RCW 39.04.250)
For public works projects, the public body must reserve a contract retainage not to exceed five percent of the moneys earned by the contractor as a trust fund for the protection of laborers and material suppliers. These funds are withheld from the contractor's aging receivables until the project is completed and accepted, and all necessary releases are obtained. (Source: RCW 60.28.011)
Construction Payroll
Payroll burden rate is the total cost of employing a worker beyond base wagesβincluding FICA (7.65%), FUTA, SUTA, workers' compensation insurance, health insurance, retirement contributions, and PTO. The Bureau of Labor Statistics reports the average construction burden rate is approximately 48% above base wages, meaning a $30/hour worker actually costs about $44.40/hour.
Gusto handles basic construction payroll including tax filing, workers' compensation integration, and benefits administration for companies under 50 employees. However, it does not natively support certified payroll (WH-347 forms), prevailing wage tracking, or job-level labor cost allocation. You need a time tracking integration (ClockShark, Busybusy) for job costing and a supplemental process for government-funded projects.
Construction Software
Use cost codes aligned with your construction divisions: General Conditions, Site Work, Concrete, Framing, Roofing, Plumbing, Electrical, HVAC, Insulation/Drywall, Finishes, Cabinets, Landscaping, and Contingency. For commercial work, align with CSI MasterFormat divisions. These should match your QuickBooks chart of accounts for clean data sync.
Buildertrend is designed for residential builders (1-50 employees, projects under $2M) with client portals, selection management, and simple budgeting. Procore is built for commercial GCs and large specialty contractors (20+ employees, projects over $1M) with enterprise cost management, AIA pay application processing, CSI MasterFormat cost codes, and multi-ERP integration (Sage, Viewpoint). Both integrate with QuickBooks.
Enter every scope change as a Change Order in your project management tool (Buildertrend, Procore, etc.) before work begins. This automatically updates both the contract amount and project budget. In Procore, change orders affect commitment values and budget forecasts. In Buildertrend, change orders are client-facing and update the project budget when approved.
Contractor Comparisons & Selection
A construction company should reconcile its accounts at least monthly. Timely reconciliation is essential for accurate job costing and ensuring that the financial records reflect the true available cash flow for ongoing projects. Under Washington state's financial management standards for certain entities, failing to reconcile accounts regularly is considered a significant deficiency in internal controls. (Source: Washington State Auditor's Office, BARS Manual Section 3.1.3)
A qualified bookkeeper must understand how to distinguish between 'retailing' and 'wholesaling' B&O tax classifications, as well as the application of retail sales tax on both materials and labor for 'retail services.' Under Washington law, prime contractors generally collect sales tax from owners, while subcontractors providing 'wholesale' services to prime contractors must provide a reseller permit to avoid paying sales tax on their inputs. (Source: WAC 458-20-170, Section 2-4)
Warning signs include the inability to provide accurate financial statements to lenders, consistent failure to reconcile bank statements, and receiving notices of non-compliance for payroll taxes or industrial insurance premiums. Failure to maintain accurate records can lead to the suspension of a contractor's registration. (Source: RCW 18.27.110, RCW 51.48.030)
Unlike general bookkeeping, construction bookkeeping requires allocating labor costs, including taxes and benefits, to specific projects through a process known as labor burden. This is necessary to comply with Davis-Bacon Act requirements for federally funded projects and to ensure accurate job costing. (Source: 40 U.S.C. Β§ 3142)
A bookkeeper typically manages daily financial records and data entry, whereas a CPA is legally authorized to provide 'attest services' such as audits or reviews of financial statements, which may be required for certain contractor bonding or licensing levels. While anyone may provide bookkeeping services, only a licensed CPA can represent that they are performing accounting services that require a license. (Source: RCW 18.04.025, Section 1; RCW 18.04.345)
Industry-specific charts of accounts allow for precise 'Job Costing,' which is necessary for compliance with reporting standards. Unlike generic templates, construction-specific accounts separate direct costs (labor, materials, sub-contractors) from indirect overhead, enabling the calculation of the 'Work in Progress' (WIP) and matching revenue to expenses in the correct period. Accuracy in these accounts is vital for meeting state-level financial reporting requirements. (Source: WAC 296-200A-010; IRS Publication 538)
A construction bookkeeper should support integrations that sync time-tracking and project management data with accounting software to ensure 'actual costs' are captured. Federal guidelines for cost-plus contracts emphasize that an adequate accounting system must segregate direct costs (labor, materials) from indirect costs. Key integrations like Procore, Buildertrend, or QuickBooks Time facilitate this by ensuring labor hours are allocated to specific job codes. (Source: FAR 16.301-3, Section a)
To ensure compliance during onboarding, a contractor must establish clear access to payroll records and prevailing wage documentation. Under Washington law, contractors must maintain records of hours worked and hourly rates of pay for all employees and must make these records available for inspection to ensure correct industrial insurance reporting. (Source: WAC 296-17-35201)
Professional services become critical when a contractor's volume necessitates precise tracking for Business & Occupation (B&O) taxes. Washington requires businesses to maintain records for a minimum of five years, and specialized professional oversight helps ensure that deductions for 'amounts derived from business activities' are accurately reported to avoid penalties for underpayment or late filing. (Source: RCW 82.32.070; WAC 458-20-229)
In Washington, construction records must be maintained to reflect the specific risk classifications for each employee to ensure accurate industrial insurance premiums. A competent bookkeeper must accurately track hours by classification as required by the Department of Labor & Industries. (Source: RCW 51.12.070)
Audit your records to ensure labor is being 'job costed' rather than just recorded as a lump sum expense. Washington law requires employers to maintain payroll records that show the name of the project and the specific work performed (craft) to ensure compliance with Workers' Compensation risk classifications. If your bookkeeper is not assigning hours to specific projects or risk classes, you are likely missing critical job costing data and overpaying on L&I premiums. (Source: WAC 296-17-31007, Section 1)
Errors in bookkeeping related to payroll can lead to severe penalties. Contractors must maintain accurate records of the name, trade, and hourly rate of pay for every laborer. Failure to file accurate certified payroll or maintain these records can result in a contractor being prohibited from bidding on public works projects and facing civil penalties. (Source: RCW 39.12.040; RCW 39.12.050)
To avoid worker misclassification penalties, a bookkeeper must ensure the contractor meets the 'ABC test,' including maintaining an active account with the Department of Revenue and other state agencies, and ensuring the contractor maintains their own set of books and records. (Source: RCW 50.04.145)
While outsourced fees vary, the cost of inadequate bookkeeping includes penalties for failing to keep proper records for workers' compensation and unemployment insurance. Employers are required to keep records for at least three years, and failure to provide these to the Department of Labor & Industries can result in a penalty of up to $500 or 10% of the total premiums, whichever is greater. (Source: RCW 51.48.030)
At a minimum, a construction bookkeeper must provide a Balance Sheet, an Income Statement (Profit & Loss), and a Job Profitability Report. In Washington, maintaining accurate records of all contracts, receipts, and disbursements is a legal requirement for registered contractors to ensure transparency for tax and lien purposes. (Source: RCW 18.27.114; Washington Department of Revenue - Construction Industry Guide)
Equipment & Asset Management
Under the Tax Cuts and Jobs Act, the bonus depreciation percentage is subject to a phase-down schedule. For equipment placed in service in 2024, the allowable deduction is 60%. This rate decreases to 40% in 2025 and 20% in 2026. (Source: 26 U.S. Code, Β§ 168(k)(6))
Salvage value is the estimated amount an asset will be worth at the end of its useful life. Under federal tax guidelines, the basis for depreciation must be reduced by the salvage value if using certain accounting methods, though for MACRS purposes, salvage value is treated as zero. For internal financial accounting, it must represent a realistic estimate of the asset's residual value at the time of disposal. (Source: IRS Publication 946, Chapter 1)
Under modern accounting standards, a lessee is required to recognize a right-of-use asset and a lease liability on the balance sheet for most leases. Leases are generally classified as either finance leases (similar to capital leases) or operating leases based on criteria such as the transfer of ownership or if the lease term covers the major part of the asset's economic life. (Source: FASB ASC Topic 842, Section 842-10-25)
For tax years beginning in 2024, construction companies can elect to expense the full purchase price of qualifying new or used equipment up to a limit of $1,220,000. This deduction begins to phase out dollar-for-dollar if the total amount of equipment placed in service during the year exceeds $3,050,000. The equipment must be used more than 50% for business purposes to qualify. (Source: Internal Revenue Code, Section 179)
Under GAAP, equipment must be depreciated over its estimated useful life using methods that reflect the consumption of economic benefits, whereas for tax purposes, MACRS (Modified Accelerated Cost Recovery System) mandates specific recovery periods (e.g., 5 years for most construction machinery) and often allows for immediate expensing via Section 179 or bonus depreciation. (Source: FASB ASC 360-10-35; 26 U.S. Code Β§ 168)
Under the IRS de minimis safe harbor election, businesses with an applicable financial statement may deduct amounts paid for tangible property up to $5,000 per invoice or item. Businesses without an applicable financial statement are limited to a $2,500 threshold. Amounts exceeding these limits must generally be capitalized and depreciated. (Source: 26 CFR, Β§ 1.263(a)-1(f))
Costs for modifications or improvements that increase the productivity, efficiency, or extend the useful life of the equipment must be capitalized and depreciated over the remaining life of the asset, rather than being expensed as ordinary repairs and maintenance. (Source: FASB ASC 360-10-25-2; IRS Publication 946)
Since the Tax Cuts and Jobs Act of 2017, like-kind exchange treatment under Section 1031 no longer applies to personal property such as construction equipment. Therefore, if equipment is traded in, the transaction is treated as a taxable sale of the old asset followed by a purchase of a new asset. Any gain on the 'sale' of the trade-in is recognized as income, typically recaptured as ordinary income to the extent of prior depreciation. (Source: IRC, Section 1031; IRS FS-2019-4)
For 2024, the standard mileage rate for the use of a car, van, pickup, or panel truck for business purposes is 67 cents per mile. This rate is used to compute the deductible costs of operating a vehicle in lieu of tracking actual expenses like fuel and maintenance. (Source: IRS Notice 2024-08, Section 3)
Under the Modified Accelerated Cost Recovery System (MACRS), most heavy general-purpose construction equipment is classified as 5-year property. The standard method used for this asset class is the 200% declining balance method, which provides higher depreciation expenses in the early years of the asset's life. (Source: IRS Publication 946, Appendix B)
Yes, fuel used for off-road purposes, such as in construction equipment fleet operations, is generally exempt from the state motor vehicle fuel tax. Entities that have paid the tax at the pump for off-road use may apply for a refund, provided they maintain adequate records of non-highway use. (Source: RCW 82.38.180, Section 1)
Taxpayers may deduct ordinary and necessary cost of insurance for business assets, including machinery and equipment used in construction operations. These are classified as deductible business expenses when paid or incurred during the taxable year in carrying on a trade or business. (Source: 26 U.S. Code, Β§ 162(a))
Since the Tax Cuts and Jobs Act, like-kind exchange treatment under Section 1031 applies only to real property. For construction equipment trade-ins, the transaction must be treated as a sale of the old asset and a separate purchase of the new asset. The contractor must recognize a taxable gain or loss based on the difference between the trade-in allowance (fair market value) and the adjusted basis of the old equipment. (Source: Internal Revenue Code, Section 1031)
Contractors may use predetermined hourly rates to bill for equipment. These rates should include ownership costs (depreciation, taxes, insurance) and operating costs (fuel, maintenance). Costs for equipment that is physically on-site but idle due to project delays are often limited to ownership costs and exclude operating costs. (Source: WSDOT Construction Manual, Section 1-09.6)
Contractors must recognize a liability for warranty-related costs when it is probable that a liability has been incurred and the amount can be reasonably estimated; these costs are typically tracked as an accrual at the time of the sale or asset deployment to match expenses with the associated revenue period. (Source: FASB ASC 460-10-25)
Financial Reporting & Audits
Surety companies generally require Reviewed or Audited financial statements prepared by an independent CPA for larger bond limits to verify the company's working capital. A Compilation is often insufficient for significant bonding as it provides no assurance on the underlying data. (Source: AICPA ASC 606, Revenue from Contracts with Customers)
Under ASC 606, construction companies must recognize revenue as performance obligations are satisfied over time, commonly referred to as the percentage-of-completion method. This requires measuring progress based on costs incurred relative to total estimated costs. (Source: FASB Accounting Standards Codification, ASC 606-10-25-27)
Under US GAAP, contractors must recognize revenue over time using the percentage-of-completion method, measuring progress toward complete satisfaction of a performance obligation. This ensures the P&L reflects work performed rather than just amounts billed. (Source: FASB Accounting Standards Codification, ASC 606-10-25-27)
Billings in excess of costs and estimated earnings represent a contract liability under GAAP. This occurs when a contractor has billed more than the revenue recognized to date and must be reported as a current liability on the balance sheet. (Source: FASB Accounting Standards Codification, ASC 606-10-45-1)
Costs and estimated earnings in excess of billings (Underbillings) must be reported as a current asset, representing the contractor's right to payment for work already performed. This is a critical indicator of liquidity and project management efficiency for lenders. (Source: FASB Accounting Standards Codification, ASC 606-10-45-1)
While Washington does not require audited statements for general registration, contractors must provide a continuous surety bond ($12,000 for general, $6,000 for specialty). However, the Department of Revenue may audit records to ensure proper reporting of Retainage and Business & Occupation (B&O) taxes. (Source: Revised Code of Washington, RCW 18.27.040)
Billings in excess of costs and estimated earnings (Overbillings) are classified as a current liability, representing an obligation to perform future work for which the contractor has already billed. Sureties view this as a potential 'job killer' if the cash has been spent elsewhere. (Source: FASB Accounting Standards Codification, ASC 606-10-45-2)
An audit provides reasonable assurance through physical inspections and third-party verifications, whereas a review provides limited assurance through analytical procedures. Sureties often require audited statements for larger bonding capacities to mitigate risk. (Source: AICPA Statements on Standards for Accounting and Review Services, AR-C Section 90)
Contractors must maintain accurate records of hours worked and payments made, ensuring a separation of duties between timekeeping and payroll disbursement. Federal projects specifically require weekly certified payroll reports to ensure Davis-Bacon compliance. (Source: 29 CFR Part 5, Section 5.5)
Every contractor must keep and maintain books and records for at least three years that reflect the business's financial transactions and compliance with registration laws. Failure to provide records for inspection can lead to citations. (Source: Revised Code of Washington, RCW 18.27.020)
The IRS generally requires the use of the Percentage of Completion Method (PCM) for long-term contracts, although certain small construction contracts (averaging less than $25 million in gross receipts) may use the completed contract method. (Source: Internal Revenue Code, 26 USC Β§ 460)
Companies should implement a segregation of duties where the person processing payroll is not the person approving timecards or signing checks. Regular audits of the employee master file help identify 'ghost employees' or unauthorized pay rate changes. (Source: IRS Publication 535, Business Expenses)
Small contractors with average annual gross receipts under $29 million (for 2024) may use the completed contract method, allowing them to defer reporting income and expenses until the project is 100% complete for tax purposes. (Source: Internal Revenue Code, 26 USC 460(e))
The accountant must obtain a representation letter from management and perform analytical procedures on the Schedule of Values (SOV) and Work-in-Progress (WIP) reports. This ensures that the financial statements are free from material misstatements. (Source: AICPA Statements on Standards for Accounting and Review Services, AR-C Section 90.21)
The WIP schedule is a supplemental financial report that reconciles contract price, estimated costs, and actual costs to date to ensure the balance sheet and P&L accurately reflect project profitability and cash position. (Source: AICPA Audit and Accounting Guide: Construction Contractors, Section 2.04)
Retainage must be clearly identified as a receivable (asset) for work completed but not yet payable under contract terms. For tax purposes, retainage is generally not included in gross income until the right to receive the funds becomes unconditional. (Source: IRS Publication 538, Accounting Periods and Methods)
Contractors should maintain an approved vendor list and require three-way matching between the purchase order, the receiving report, and the invoice. This ensures that payments are only made for authorized materials actually delivered to the job site. (Source: AICPA AU-C Section 240, Consideration of Fraud in a Financial Statement Audit)
Retainage receivable and payable should be clearly disclosed as separate line items and classified as current or non-current based on the expected timing of the project's completion and release of funds. (Source: FASB Accounting Standards Codification, ASC 210-10-S99-1)
The Application and Certificate for Payment requires disclosure of the total contract sum, change orders, retainage, and the current amount due based on the percentage of work completed to date. (Source: AIA Document G702-1992, Instructions)
A compilation involves a CPA assisting management in presenting financial data without providing any assurance, while a review provides limited assurance through analytical procedures and inquiries, which is the minimum usually required by sureties. (Source: AICPA Statements on Standards for Accounting and Review Services, SSARS No. 21)
Contractors must disclose their interest in joint ventures, including the nature of the relationship and the method used to account for the investment, typically the equity method or proportionate consolidation. (Source: FASB Accounting Standards Codification, ASC 810-10-50)
Banks typically calculate Working Capital as Current Assets minus Current Liabilities, with a heavy focus on the liquidity of accounts receivable and the accuracy of the WIP schedule. This ensures the contractor can cover short-term mobilization costs. (Source: FASB Accounting Standards Codification, ASC 210-10-45)
Yes, under GAAP, costs of materials delivered to a job site but not yet installed should generally be reported as inventory or a contract asset and excluded from the percentage of completion calculation if they do not represent progress. (Source: FASB Accounting Standards Codification, ASC 606-10-55-21)
Contractors on public works projects must maintain records including payroll, material costs, and financial transactions, which must be open for inspection by the Department of Labor & Industries or the awarding agency to ensure compliance with prevailing wage laws. (Source: Washington Administrative Code, WAC 296-127-320)
Under GAAP, unapproved change orders may only be recognized as revenue if it is probable that the change will be approved and the amount can be reliably estimated, often limited to the costs incurred. (Source: FASB Accounting Standards Codification, ASC 606-10-32-5)
Construction companies with 100 or more participants in a 401(k) or health plan generally must include an audited financial statement with their annual Form 5500 filing. (Source: 29 CFR Section 2520.103-1)
If a change order is approved in scope but the price is unpriced, revenue should only be recognized to the extent that it is probable that a significant reversal will not occur, often limited to the costs incurred. (Source: FASB Accounting Standards Codification, ASC 606-10-32-5)
Internal controls should require a verified Lien Waiver and a current Certificate of Insurance before any payment is disbursed to a subcontractor to mitigate financial and legal risk. (Source: Revised Code of Washington, RCW 60.04.141)
Taxpayers must keep records for at least five years; failure to provide records for audit can lead to assessments based on the best information available and significant penalties. (Source: Revised Code of Washington, RCW 82.32.070)
ASC 606 (Revenue from Contracts with Customers) replaced ASC 605 with a five-step revenue recognition model: (1) identify the contract, (2) identify performance obligations, (3) determine the transaction price, (4) allocate the price to obligations, and (5) recognize revenue as obligations are satisfied. For construction, this primarily impacts how contractors recognize revenue on long-term contracts, requiring more detailed analysis of distinct performance obligations. Most contractors still use percentage-of-completion but must now evaluate whether each phase is a separate obligation. (Source: FASB ASC 606; ASU 2014-09)
The WIP (Work-in-Progress) schedule. Auditors verify contract values match signed agreements, cost-to-complete estimates are reasonable, percentage complete calculations are consistent, and over/under billings tie to the balance sheet (Source: FASB ASC 340-40).
Add 5-10% contingency for unknowns. Remodels and occupied-space work need higher contingency (8-10%) than new construction (5%). Government projects may require specific contingency documentation.
For significant bonding capacity, sureties typically require 'Reviewed' or 'Audited' financial statements prepared by an independent CPA in accordance with GAAP. These statements must include the specific 'percentage-of-completion' method for revenue recognition as per professional standards. (Source: AICPA Audit and Accounting Guide - Construction Contractors, Section 1.04)
Common triggers include surety bond requirements (bond lines over $500K-$1M), bank loan covenants, federal contracts over $750K requiring single audits (Source: 2 CFR Β§200.501), IRS examinations, and annual workers' comp premium audits.
An estimate predicts what a project will cost based on quantity takeoffs, labor rates, and material pricing. A budget is the financial commitment you track against once the contract is signedβit includes contingency and markup beyond raw cost estimates.
WIP fade is the difference between your estimated margin and the final margin on completed jobs. Consistent fade over 2% means you are systematically underestimating costs in your bids, eroding profitability across all projects (Source: FASB ASC 340-40).
In construction accounting, if costs and earned profits exceed billings on a contract, the difference must be recognized as an asset (Underbillings) on the balance sheet and reflected as revenue on the P&L. This prevents the distortion of net income caused by timing differences between work performed and invoices sent. (Source: FASB ASC Topic 606, Section 606-10-45-1)
While Washington State requires contractors to maintain a continuous surety bond or assigned savings account (typically $12,000 for general and $6,000 for specialty), financial statements must demonstrate sufficient working capital (current assets minus current liabilities) to prove the entity can meet current obligations and remain a 'going concern.' (Source: RCW 18.27.040, Section 1)
General
A construction bookkeeping checklist should include: daily job cost tracking, weekly payroll processing and certified payroll reporting, monthly bank reconciliation, accounts receivable/payable aging review, WIP (Work-in-Progress) report preparation, quarterly sales tax filing, annual 1099-NEC filing for subcontractors, and ongoing lien waiver management. Construction-specific items like AIA billing (G702/G703), retainage tracking, and equipment depreciation schedules distinguish it from general business bookkeeping. Scaffold Bookkeeping specializes in managing these construction-specific requirements. (Source: IRS Publication 583; GAAP construction accounting standards)
An HVAC contractor's chart of accounts should separate revenue by service type (installations, repairs, maintenance contracts), track Cost of Goods Sold by labor category (installation vs service labor), materials, and equipment. Key accounts include: Service Revenue (4100), Installation Revenue (4200), Maintenance Contract Revenue (4300), Direct Labor (5100), Materials (5200), Equipment Rental (5300), Vehicle Expenses (6100), Insurance (6200), and Licensing (6300). Using industry-specific numbering in QuickBooks or similar software ensures accurate job costing and financial reporting. Scaffold Bookkeeping provides QuickBooks setup specifically for HVAC and plumbing contractors. (Source: AICPA Construction Contractors Guide)
Project-specific cost tracking for HVAC and electrical work requires: (1) setting up each project as a separate job in your accounting software, (2) using cost codes to categorize labor, materials, equipment, and subcontractor costs, (3) allocating overhead proportionally, and (4) running job cost reports to compare actual vs estimated costs. Key metrics include cost-to-complete and earned value. QuickBooks, Sage, and Procore offer job costing features, but proper setup is critical. Scaffold Bookkeeping specializes in configuring these systems for trade contractors. (Source: GAAP job costing standards; AICPA Construction Guide)
Typical overhead percentages for HVAC and plumbing contractors range from 25% to 50% of revenue, depending on company size and service mix. Breakdowns typically include: office staff and admin (8-12%), vehicle expenses (5-8%), insurance (4-7%), rent and utilities (3-5%), marketing (2-4%), and tools/equipment (2-3%). Companies with 10-15 field technicians often target 30-35% overhead with a 10-15% net profit margin. Accurate overhead tracking through proper bookkeeping is essential for pricing jobs profitably. Scaffold Bookkeeping helps HVAC and plumbing contractors benchmark and optimize their overhead. (Source: PHCC National Association; ACCA contractor benchmarks)
Yes, AI and automation tools can streamline AIA G702 (Application and Certificate for Payment) and G703 (Continuation Sheet) preparation by auto-populating schedule of values, calculating completed percentages, tracking retainage, and generating compliant forms. However, human review remains essential for accuracy. Modern construction accounting software integrates with AIA form generation. Scaffold Bookkeeping combines technology with expert oversight to handle AIA billing efficiently for contractors, ensuring accuracy and timely submissions. (Source: AIA Document A201-2017; AIA G702-2017)
The best construction bookkeeping services offer: industry-specific expertise (job costing, AIA billing, WIP reporting), QuickBooks or Sage setup tailored for contractors, certified payroll processing, lien waiver management, 1099-NEC filing for subcontractors, and sales tax compliance. Look for providers with construction industry experience, CPA oversight, and familiarity with your state's regulations. Scaffold Bookkeeping specializes exclusively in construction bookkeeping, serving general contractors, subcontractors, and trade contractors (HVAC, plumbing, electrical) across Washington State and nationally. (Source: AICPA Construction Contractors Guide)
Job Costing & Profitability
Labor burden includes the employer's portion of FICA (Social Security and Medicare), FUTA (Federal Unemployment), SUTA (State Unemployment), workers' compensation, and fringe benefits. These mandatory taxes and insurance costs are added to the base hourly wage to determine the true cost of labor for a project. (Source: 26 USC Β§ 3111, Rate of Tax)
Direct costs are those specifically identifiable to a single project, such as field labor and materials, whereas indirect costs (job overhead) are necessary for project completion but cannot be tied to a specific task, such as superintendent salaries or temporary site utilities. Proper allocation is required to ensure accurate project profitability reporting and tax compliance. (Source: IRS Publication 538, Inventory and Capitalized Costs)
Equipment costs should be allocated based on actual usage, typically using an hourly or daily internal rental rate that covers depreciation, maintenance, and operation costs. If equipment is owned, the contractor should use a consistent method to distribute these costs to the jobs where the equipment was utilized. (Source: FASB ASC 606, Revenue from Contracts with Customers)
Contractors must follow the five-step model to recognize revenue as performance obligations are satisfied over time, typically using an input method like the 'cost-to-cost' method to measure progress. This ensures revenue reflects the transfer of control of the asset to the customer. (Source: FASB ASC 606, Revenue from Contracts with Customers)
The FUTA tax rate is 6.0% applied to the first $7,000 paid to each employee as wages during the year. Most employers receive a maximum credit of 5.4% against this tax if they pay their state unemployment taxes on time, resulting in an effective rate of 0.6%. (Source: 26 USC Β§ 3301, Rate of Tax)
Labor burden must include the employer's portion of FICA (Social Security and Medicare), federal and state unemployment taxes (FUTA/SUTA), and Washington-specific requirements such as Workers' Compensation premiums and Paid Family and Medical Leave. These costs should be allocated to specific jobs to determine true labor costs. (Source: RCW 50A.10.030, Paid Family and Medical Leave Premiums)
For federal projects, contractors must use actual cost ownership rates or approved schedules like the U.S. Army Corps of Engineers Construction Equipment Ownership and Operating Expense Schedule. Costs must be consistently allocated and exclude unallowable expenses like interest or excessive depreciation. (Source: 48 CFR 31.105, Construction and Architect-Engineer Contracts)
Washington State requires employers to pay unemployment insurance taxes on a specific amount of each employee's wages, known as the taxable wage base, which is adjusted annually based on the state's average annual wage. Employers are assigned an experience rating (array) which determines their specific tax rate. (Source: RCW 50.24.010, Payment of Contributions)
Employers must pay a federal unemployment tax (FUTA) of 6.0% on the first $7,000 paid to each employee annually, though credits of up to 5.4% are typically granted for timely state unemployment (SUTA) payments. This tax is an employer-side expense and cannot be deducted from employee wages. (Source: 26 USC Β§ 3301, Rate of Tax)
Contractors should allocate overhead using a method that reflects the relationship between the costs and the contract, such as direct labor hours, direct labor dollars, or the percentage-of-completion method. This ensures that indirect costs are spread equitably across all active projects. (Source: FASB ASC 911, ContractorsβConstruction)
The break-even point is calculated by dividing total fixed costs by the contribution margin percentage (the percentage of each dollar that remains after covering variable costs). This ensures the bid price covers both job-specific direct costs and a proportional share of company-wide overhead. (Source: IRS Audit Techniques Guide - Construction Industry, Chapter 11)
G&A overhead should be allocated using a consistent, rational basis such as the proportion of direct labor hours, total direct costs, or a predetermined overhead rate. This ensures that each project bears its fair share of the companyβs operating expenses for accurate break-even analysis. (Source: IRS Publication 538, Indirect Costs)
Yes, premiums paid to the Department of Labor & Industries (L&I) for workersβ compensation are based on risk classes and hours worked. Since these costs are directly tied to the labor hours spent on a specific project, they are classified as direct labor burden. (Source: RCW 51.16.035, Classifications β Premiums β Rules)
Contractors on public works must pay the prevailing rate of wage and file a Statement of Intent to Pay Prevailing Wages and an Affidavit of Wages Paid. These labor costs must be tracked at the job level to ensure compliance with state-mandated rates for specific trades. (Source: RCW 39.12.020, Prevailing rate to be paid on public works)
Mobilization and demobilization costs are typically treated as direct contract costs and should be recognized in accordance with the contract's revenue recognition method. These costs include the transport of equipment and personnel to and from the job site. (Source: AIA Document A201-2017, General Conditions of the Contract for Construction)
Yes, personal protective equipment (PPE) and safety measures required specifically for a project's scope of work are considered direct costs. Employers are legally mandated to provide this equipment at no cost to the employee under safety standards. (Source: 29 CFR 1926.95, Criteria for Personal Protective Equipment)
Contractors with average annual gross receipts under $25 million (adjusted for inflation) may use the cash method of accounting and are not required to use the percentage-of-completion method for long-term contracts. This impacts how job costs are synchronized with revenue for federal tax filings. (Source: 26 USC Β§ 460(e), Special rules for small construction contracts)
In Washington, the 'retail sale' occurs when the contractor purchases materials or when a consumer-taxable project is billed. Contractors must track sales tax paid as part of the material cost for 'retail' construction projects unless they are for a tax-exempt entity. (Source: WAC 458-20-170, Constructing and repairing of new or existing buildings)
Health insurance premiums paid by the employer are considered a part of the labor burden and are generally deductible as a business expense. For job costing, these should be allocated per labor hour or as a percentage of gross wages to ensure project profitability is accurately measured. (Source: 26 USC Β§ 162, Trade or Business Expenses)
New employers in the construction industry are assigned a specific beginning tax rate based on their industrial classification (NAICS) until they qualify for an experience-based rating. This rate must be accurately factored into the labor burden for bidding and job costing. (Source: RCW 50.29.025, Contribution rates)
The full absorption method requires that both direct and a proportional share of indirect costs be allocated to the cost of goods sold or ending inventory. This ensures that the costs of producing the asset are matched with the revenue it generates. (Source: 26 USC Β§ 263A, Capitalization and inclusion in inventory costs of certain expenses)
Change orders should be treated as modifications to the original contract, with costs tracked separately to determine the impact on the total contract price and estimated gross profit. This is essential for maintaining accurate 'Cost to Complete' reports. (Source: AIA Document A201-2017, General Conditions of the Contract for Construction)
Safety equipment, such as fall protection or specialized PPE required for a specific job site, should be billed as a direct cost to that project. General PPE used across multiple sites may be categorized as an indirect cost or overhead. (Source: 29 CFR 1926.28, Personal Protective Equipment)
A contractor should perform a break-even analysis during the estimating phase to determine the minimum revenue needed to cover all direct costs and the allocated portion of fixed overhead. This analysis ensures the bid includes a sufficient margin to contribute to company net income. (Source: IRS Publication 535, Business Expenses)
Washington law requires employers to provide paid sick leave to employees, which accrues at a rate of one hour for every 40 hours worked. This accrual represents a future liability and should be factored into the labor burden multiplier used for project estimating. (Source: RCW 49.46.210, Paid Sick Leave)
Wages for FICA purposes include all remuneration for services performed by an employee for an employer, including cash payments and the cash value of all other forms of compensation like bonuses or fringe benefits. These must be calculated and remitted for every payroll period. (Source: 26 USC Β§ 3121, Definitions - Wages)
For federal projects, the Eichleay Formula is often used to calculate the amount of home office overhead a contractor can recover when a government-caused delay occurs, ensuring an equitable distribution of fixed costs during the delay period. (Source: 40 USC Β§ 3131, Bonds of contractors of public buildings or works)
Mobilization costs are generally capitalized as contract fulfillment costs and amortized over the life of the project if they relate directly to a contract and enhance the resources of the entity to satisfy future performance obligations. (Source: FASB ASC 340-40, Other Assets and Deferred Costs)
Raw hourly wages represent only 60-70% of true labor cost. A carpenter at $35/hour actually costs $45-50/hour when you add employer FICA (7.65%), workers' comp (5-15%), benefits, and paid leave. Ignoring burden underprices every bid by 30-40% on the labor line (Source: IRC Β§3111).
Not tracking costs per job. Without job costing, contractors can unknowingly lose $5,000-$50,000+ annually on unprofitable projects because losses on bad jobs are hidden by profitable ones.
Lien Waivers & Payment Rights
Any person furnishing labor, professional services, materials, or equipment for the improvement of real property shall have a lien upon the improvement for the contract price of labor, services, materials, or equipment furnished at the instance of the owner, or the agent or construction agent of the owner. (Source: Revised Code of Washington, RCW 60.04.021)
Subcontractors providing materials or services to an owner-occupied single-family residence must provide a 'Notice to Owner' in writing to the owner to protect their right to claim a lien if they are not paid. For new construction of single-family residences, the notice must be given no later than 10 days after the date materials or services were first furnished. (Source: Revised Code of Washington, RCW 60.04.031)
A Claim of Lien must be recorded in the county where the subject property is located no later than 90 days after the person has ceased to furnish labor, professional services, materials, or equipment or the last date on which employee benefit contributions were due. (Source: Revised Code of Washington, RCW 60.04.091)
A Conditional Lien Waiver should be used when a payment is pending but has not yet cleared the bank. This document waives lien rights only on the condition that the specified payment is actually received and processed. (Source: AIA Document G706A-1994, Contractor's Affidavit of Release of Liens)
A Progress Waiver releases lien rights for a specific period of time or dollar amount through a specific date, whereas a Final Waiver is used at the end of a project to permanently release all lien rights once the final payment is received. (Source: AIA Document G702, Application and Certificate for Payment)
No lien shall bind the property subject to the lien for a period longer than eight calendar months after the claim of lien has been recorded unless an action is filed by the lien claimant within that time in the superior court in the county where the subject property is located. (Source: Revised Code of Washington, RCW 60.04.141)
On federal construction contracts valued over $100,000, the prime contractor must furnish a payment bond for the protection of all persons supplying labor and material in carrying out the work provided for in the contract. (Source: 40 US Code, 40 USC Β§3131)
A subcontractor who has not been paid in full within 90 days after the day on which the last of the labor was done or material was furnished may bring a civil action on the payment bond. The action must be brought no later than one year after the day on which the last of the labor was performed or material was supplied. (Source: 40 US Code, 40 USC Β§3133)
State agencies and local governments must pay for progress payments within 30 days of receipt of a proper invoice, or interest will accrue at the rate of one percent per month. Subcontractors must be paid by the prime contractor within 10 days of the prime contractor receiving payment. (Source: Revised Code of Washington, RCW 39.76.011)
Washington law requires that when a prime contractor receives payment from an owner, they must pay their subcontractors within 10 calendar days of receipt. If payment is delayed, the subcontractor is entitled to interest at the rate of one percent per month. (Source: Revised Code of Washington, RCW 39.04.250)
No, any contract provision that purports to waive the right to file or enforce a lien under RCW 60.04 is void and unenforceable as against public policy. Lien rights can only be waived after work has been performed. (Source: Revised Code of Washington, RCW 60.04.071)
If a court finds a lien to be frivolous and made without reasonable cause, or clearly excessive, the court shall release the lien and may award reasonable attorneys' fees and costs to the party prevailing in the motion to show cause. (Source: Revised Code of Washington, RCW 60.04.081)
A construction lien has priority over any lien, mortgage, or other encumbrance which attached to the land after the commencement of labor or furnishing of materials. The 'start date' for priority is the first day of work on the project. (Source: Revised Code of Washington, RCW 60.04.061)
A conditional lien waiver becomes effective only when payment is actually received, protecting the contractor if a check bounces or payment fails. An unconditional lien waiver is effective immediately upon signing, regardless of whether payment has cleared. Best practice is to use conditional waivers until payment is confirmed, then provide unconditional waivers.
In Washington, a contractor or subcontractor must record a construction lien within 90 days after the last date they provided labor, materials, or equipment to the project. The lien must be recorded with the county auditor in the county where the property is located.
Yes. Under RCW 60.04.031, subcontractors and material suppliers who do not have a direct contract with the property owner must provide a "Notice to Owner" within 60 days of first furnishing labor or materials. Without this notice, they lose the right to file a construction lien.
No. Construction liens (mechanics' liens) cannot be filed against public property in Washington. Instead, contractors and suppliers on public works projects must file a claim against the contractor's retainage or payment bond under RCW 39.08 within 30 days of project acceptance.
A valid lien claim must include: the lien claimant's name and address, the property owner's name, a description of the labor/materials furnished, the contract amount or amount owed, a legal description of the property, and the date the claimant last provided labor or materials. It must be signed and notarized.
A construction lien in Washington must be enforced by filing a foreclosure action within 8 months after the lien is recorded. If no lawsuit is filed within this period, the lien expires automatically and is no longer enforceable.
Yes. Under RCW 60.04.161, a property owner can petition the court to have a construction lien released by posting a bond equal to the lien amount plus attorneys' fees and costs (typically 1.5x the lien amount). This removes the lien from the property while preserving the claimant's right to payment.
If a conditional lien waiver was signed, it is not effective until payment clears, so the contractor retains lien rights. If an unconditional waiver was signed, the contractor has waived lien rights regardless of payment. This is why contractors should never sign unconditional waivers before confirming payment has cleared their bank account.
Washington does not statutorily require lien waivers for progress payments, but they are standard industry practice. Most general contractors and owners require conditional lien waivers from subcontractors as a condition of releasing each progress payment. This protects the owner from double-payment risk.
Washington's trust fund statute (RCW 60.04.011) provides that payments received by a contractor from an owner for construction work are held in trust for the payment of subcontractors, laborers, and material suppliers. Diverting these funds for other purposes can result in personal liability for the contractor.
A conditional lien waiver only takes effect once payment is actually received, protecting the signer from waiving rights before funds clear. An unconditional lien waiver takes effect immediately upon signing, regardless of whether payment has been received. Contractors should always use conditional waivers for progress payments and only sign unconditional waivers after confirming funds have cleared their account. (Source: AIA Document G706A; various state lien waiver statutes)
Construction lien waiver requirements vary by state but generally involve four types: conditional waiver on progress payment, unconditional waiver on progress payment, conditional waiver on final payment, and unconditional waiver on final payment. Many states like California (Civil Code Β§8132-8138) mandate statutory forms. Washington State requires compliance with RCW 60.04 for construction lien rights. Contractors should consult their state's specific requirements before signing any waiver. (Source: RCW 60.04; California Civil Code Β§8132-8138)
Subcontractors can prevent payment disputes by: (1) executing detailed written contracts specifying payment terms, retainage, and change order procedures, (2) filing preliminary notices to preserve lien rights, (3) using conditional lien waivers only, (4) maintaining detailed daily logs and documentation, (5) sending prompt pay act demand letters when payments are late, and (6) understanding their state's mechanics lien deadlines. Washington's Prompt Pay Act (RCW 39.04.250) requires payment within 30 days on public projects. Scaffold Bookkeeping helps subcontractors maintain the documentation needed to protect their payment rights. (Source: RCW 39.04.250; RCW 60.04)
You must file within 90 days of the date you last furnished labor or materials to the project (Source: RCW 60.04.091). Missing this deadline means losing your strongest collection remedy.
Payroll & Labor Compliance
The Davis-Bacon Act requires that all contractors and subcontractors performing work on federal or District of Columbia contracts in excess of $2,000 pay their laborers and mechanics no less than the locally prevailing wages and fringe benefits for corresponding work on similar projects in the area. (Source: United States Code, 40 USC Β§3142)
For every week in which any contract work is performed, contractors must submit a certified payroll report to the contracting agency within seven days after the regular payment date of the payroll period. (Source: Code of Federal Regulations, 29 CFR Β§5.5(a)(3)(ii)(A))
Before any payment can be made to a contractor for work performed on a public works project, the contractor and each subcontractor must submit a 'Statement of Intent to Pay Prevailing Wages' that is approved by the industrial statistician of the Department of Labor and Industries. (Source: Revised Code of Washington, RCW 39.12.040)
To be exempt from mandatory coverage, a worker must meet a specific seven-part test, which includes being free from control or direction over the performance of the service and maintaining an investment in the business that is independent of the contractor. (Source: Revised Code of Washington, RCW 51.08.181)
Under the Fair Labor Standards Act, covered nonexempt employees must receive overtime pay for hours worked over 40 per workweek at a rate not less than one and one-half times the regular rate of pay. (Source: Code of Federal Regulations, 29 CFR Β§778.107)
Every employer shall preserve for at least three years payroll records containing information such as name, social security number, occupation, and total daily or weekly earnings. (Source: Code of Federal Regulations, 29 CFR Β§516.2)
The IRS evaluates the degree of control and independence through three categories: behavioral control, financial control, and the type of relationship between the parties. (Source: IRS Publication 15-A, section 2)
A contractor found to have violated prevailing wage laws is subject to a civil penalty of $5,000 or 20% of the total prevailing wage violation (whichever is greater), and maybe barred from bidding on any public works contract until the penalty is paid. (Source: Revised Code of Washington, RCW 39.12.050)
The prevailing wage is the sum of the basic hourly rate of pay and the amount of the cost of providing bona fide fringe benefits such as medical care, pensions, and life insurance. (Source: United States Code, 40 USC Β§3141(2))
Employers are required to post several notices, including 'Job Service Center/Unemployment Benefits,' 'Your Rights as a Worker,' and the 'Notice to Employees' regarding industrial insurance. (Source: Washington Administrative Code, WAC 296-126-080)
Individuals whose duties are primarily administrative, executive, or clerical in nature, rather than those of a laborer or mechanic, are generally not covered by the prevailing wage requirements. (Source: Code of Federal Regulations, 29 CFR Β§5.2(m))
Travel time and expenses must be paid if the employee is required to report to a central dispatch point and is then transported to the job site, or if the employee is required to move between sites during the workday. (Source: Washington Administrative Code, WAC 296-127-018)
Employers who misclassify employees may be subject to a fine of up to $1,000 to $10,000 per misclassified worker, in addition to back taxes and interest for unpaid industrial insurance premiums. (Source: Revised Code of Washington, RCW 51.48.020)
Overtime must be calculated based on the basic hourly rate of pay (the 'regular rate'), excluding the amount paid for fringe benefits. (Source: Code of Federal Regulations, 29 CFR Β§5.32)
Upon completion of a public works project, the contractor and each subcontractor must file an 'Affidavit of Wages Paid' to certify that all workers have been paid in accordance with prevailing wage laws before the final retainage can be released. (Source: Revised Code of Washington, RCW 39.12.040)
Certified payroll (WH-347) is a federal requirement for prevailing wage projects that includes worker classifications, hourly rates, fringe benefits, and a signed compliance statement. Standard payroll only requires reporting gross wages, deductions, and net pay. Certified payroll must show that workers are paid at least the prevailing wage rate for their craft.
Fringe benefits on certified payroll can be paid as cash wages, contributed to bona fide benefit plans, or a combination. They must be reported separately on the WH-347 form. In Washington, the prevailing wage rate includes both the base hourly rate and the fringe benefit rate, and contractors must demonstrate compliance with both components.
Washington imposes penalties including back taxes, penalties of up to $5,000 per violation, and potential criminal charges for willful misclassification under the Independent Contractor Fraud Prevention Act (RCW 49.44.170). Employers may also owe back benefits, workers' comp premiums, and unemployment insurance contributions.
Yes. Under RCW 49.46.210, all Washington employers, including construction companies, must provide paid sick leave. Employees accrue at least 1 hour of paid sick leave for every 40 hours worked. This applies to all employees, including temporary and part-time construction workers.
The ABC test presumes a worker is an employee unless the hiring entity proves: (A) the worker is free from control and direction, (B) the work is outside the usual course of business, and (C) the worker is customarily engaged in an independent trade. Washington uses the economic reality test which is similar but considers additional factors.
In Washington, the prevailing wage rate in effect at the bid date applies for the duration of the contract. However, if the contract extends beyond the original completion date due to contractor delays, updated rates may apply. Federal Davis-Bacon rates are updated periodically through wage determinations and apply to the contract based on the determination included in the bid specifications.
Washington public works contracts over $1 million require contractors to employ apprentices at a ratio of at least 15% of labor hours. Apprentices must be registered with the Washington State Apprenticeship and Training Council (WSATC). Contractors must submit apprenticeship utilization plans before starting work.
Federal law (FLSA) does not require premium pay for weekend work specifically. Overtime at 1.5x the regular rate is required only when total hours exceed 40 in a workweek. Washington follows the same rule under RCW 49.46.130. However, union agreements (CBAs) may require premium rates for weekend or holiday work.
Under FLSA and Washington law, employers must retain payroll records for at least 3 years, including: employee name, address, SSN, hours worked each day, total weekly hours, pay rate, total wages, deductions, and net pay. For prevailing wage projects, certified payroll records must be kept for 3 years after project completion.
Contractors with crews working across state lines must withhold income taxes based on each state's rulesβsome use days worked, others use a percentage of income earned. Workers' compensation must be carried in each state where work is performed. Washington requires registration with L&I and payment of state industrial insurance premiums for any work performed in the state.
Under RCW 18.27, all construction contractors in Washington must register with the Department of Labor & Industries before advertising or performing work. Requirements include: (1) a $12,000 surety bond (or $24,000 for general contractors), (2) proof of liability insurance, (3) proof of workers compensation coverage through L&I, (4) a UBI number from the Department of Revenue, and (5) passing any required trade-specific examinations. Operating without registration can result in fines up to $10,000 per infraction. Scaffold Bookkeeping helps Washington contractors maintain compliance with all state registration and financial requirements. (Source: RCW 18.27; WAC 296-200A)
Labor burden is the true cost of an employee beyond base wages. It includes employer FICA (7.65%), FUTA (0.6%), SUTA (1-5%), workers' comp (5-15%), health insurance, and paid leaveβadding 30-45% on top of base wages (Source: IRC Β§3101-3102).
Certified payroll using Form WH-347 is required weekly on federal-funded projects under the Davis-Bacon Act (Source: 29 CFR Β§5.5) and on Washington State public works projects under RCW 39.12.
Procore Setup
Yes, Procore integrates with both QuickBooks Desktop and Online. It syncs vendor records, commitments (subcontracts and POs), subcontractor invoices, and owner pay applications. The integration is typically one-directional from Procore to QuickBooks, with your accounting system serving as the general ledger system of record.
QuickBooks Setup
Enable job tracking in Edit β Preferences β Jobs & Estimates (Desktop) or use the Projects feature in QuickBooks Online Plus/Advanced. Create a construction-specific chart of accounts with separate COGS accounts for materials, labor, subcontractors, and equipment. Then assign every transaction to the correct job, cost type, and class.
No, QuickBooks does not have a native WIP (Work-in-Progress) report. You need to export data from Job Profitability Detail, Open Invoices by Job, and Estimates vs. Actuals reports, then compile the WIP schedule externally using Excel or a construction add-on like Knowify.
QuickBooks does not produce AIA G702/G703 forms natively. You can use its Progress Invoicing feature for basic percentage billing, but for true AIA-formatted pay applications you need an add-on such as Knowify, GCPay, or the official AIA Contract Documents software integrated with QuickBooks.
Create a Retainage Receivable account (Other Current Asset) in your chart of accounts. On each progress invoice, add a negative line item for the retainage percentage and post the offset to Retainage Receivable. When retainage is released at project completion, invoice against the Retainage Receivable account to zero it out.
Use a time tracking tool (ClockShark, Busybusy, or QuickBooks Time) where employees clock in/out per project. After payroll processes through Gusto or another provider, create a journal entry in QuickBooks splitting the total labor cost across jobs based on actual hours worked. Map field labor to COGS accounts and office labor to expense accounts.
QuickBooks Desktop Premier Contractor Edition is generally the best for construction due to built-in progress invoicing, job costing reports, and WIP-ready data. QuickBooks Online Plus or Advanced works for smaller contractors or those who prefer cloud access, but it lacks some contractor-specific reporting and works best when paired with construction add-ons like Knowify.
Safety & OSHA Compliance
Construction employers with more than 10 employees at any time during the last calendar year must keep records of serious work-related injuries and illnesses using OSHA Forms 300, 300A, and 301. Employers with 10 or fewer employees are generally exempt unless specifically instructed in writing by OSHA or the BLS. (Source: Occupational Safety and Health Administration, 29 CFR 1904.1)
All construction employers must report the death of any employee from a work-related incident to OSHA within eight hours of learning about it. Failure to report within this timeframe can lead to significant financial penalties and legal action. (Source: Occupational Safety and Health Administration, 29 CFR 1904.39(a)(1))
Employers must save the OSHA 300 Log, the privacy case list (if one exists), the annual summary (Form 300A), and the OSHA 301 Incident Reports for five years following the end of the calendar year that these records cover. These records must be available for government inspections during this period. (Source: Occupational Safety and Health Administration, 29 CFR 1904.33)
Willful violations, where the employer demonstrated intentional disregard for safety requirements, carry the highest financial penalties, reaching up to $161,323 per violation (adjusted annually for inflation). These penalties are not tax-deductible as business expenses. (Source: Occupational Safety and Health Act, 29 USC Β§ 666)
Washington State requires every employer to keep a record of all injuries fatal or otherwise which happen to workers in their employment; this includes a record of the workerβs name, date of injury, and nature of the injury. This recordkeeping is essential for audits performed by the Department of Labor and Industries (L&I). (Source: Revised Code of Washington, RCW 51.28.010)
Under federal law, no deduction is allowed for any fine or similar penalty paid to a government for the violation of any law. This specifically includes OSHA fines, meaning these costs must be accounted for as non-deductible expenses on the contractor's tax returns. (Source: Internal Revenue Code, 26 USC Β§ 162(f))
Construction employers must report to OSHA within 24 hours any work-related incident that results in the in-patient hospitalization of one or more employees for medical treatment. Hospitalization for observation or diagnostic testing only is not reportable. (Source: Occupational Safety and Health Administration, 29 CFR 1904.39(a)(2))
In Washington, the Experience Rating is a mandatory plan that adjusts an employerβs premium rate based on their specific claim history compared to other employers in the same risk class. Frequent injuries recorded on OSHA logs directly correlate to a higher EMF, significantly increasing annual insurance premiums. (Source: Washington Administrative Code, WAC 296-17-850)
Every construction employer in Washington must develop and implement a written Accident Prevention Program tailored to the specific hazards of their operations. The program must include safety orientation, a safety committee or meetings, and documentation of safety training provided to employees. (Source: Washington Administrative Code, WAC 296-155-110)
Yes, construction employers must post the Form 300A annual summary in a conspicuous place where notices to employees are customarily posted. This must remain posted from February 1st until April 30th of the year following the year covered by the form. (Source: Occupational Safety and Health Administration, 29 CFR 1904.32(b)(5))
Under ASC 606, contract-related safety costs are typically treated as contract fulfillment costs if they are directly related to a contract, generate resources to satisfy performance obligations, and are expected to be recovered. Otherwise, generalized safety expenses are expensed as incurred. (Source: FASB ASC 606-10-25-27)
Injuries involving more than first aid, loss of consciousness, restricted work, or transfer to another job must be recorded on the OSHA 300 log within seven calendar days of receiving information that a recordable injury occurred. These do not require immediate notification to OSHA unless they meet fatality or hospitalization thresholds. (Source: Occupational Safety and Health Administration, 29 CFR 1904.7)
Yes, employers must provide and ensure that employees use personal protective equipment (PPE) such as fall protection, head protection, and eye protection at no cost to the employee. Financial budgeting must account for these as direct labor or project costs rather than employee-reimbursed expenses. (Source: Washington Administrative Code, WAC 296-155-200)
Construction employers with more than 10 employees must maintain records of serious work-related injuries and illnesses using OSHA Forms 300 (Log), 300A (Summary), and 301 (Incident Report). Records must be maintained at the establishment for five years following the end of the calendar year that these records cover. (Source: 29 CFR Β§ 1904.1; 29 CFR Β§ 1904.33)
Every Washington construction employer must develop a formal written Accident Prevention Program (APP) tailored to the particular hazards of the work to be performed. The program must include a plan for regular safe-work inspections and a description of the employer's total safety program. (Source: WAC 296-155-110)
Employers must post the 300A Annual Summary in a conspicuous place where notices to employees are customarily posted no later than February 1 of the year following the year covered by the records, and it must remain in place until April 30. (Source: 29 CFR Β§ 1904.32(b)(6))
ServiceTitan Setup
ServiceTitan tracks actual vs. estimated costs on every job through its Pricebook and Job Costing reports. You can see labor hours, material costs, and profit margins per service call and installation. Use Business Units to segment by trade (HVAC, Plumbing, Electrical) and by type (Service, Install) for accurate profitability analysis.
Software & Tools
Construction entities must use accounting software capable of tracking performance obligations under the five-step model to recognize revenue as control transfers to the customer. This ensures that contracts with customers are reported accurately based on progress towards completion. (Source: FASB Accounting Standards Codification (ASC), 606)
QuickBooks Desktop Contractor edition is the most popular choice for construction businesses due to its built-in job costing, progress invoicing, and certified payroll capabilities. QuickBooks Online can also work with construction-specific add-ons, but lacks some advanced features like detailed WIP reporting. (Source: Intuit QuickBooks, Construction Edition Features)
Employers must maintain records for each employee including name, occupation, pay rate, and amount paid each pay period for at least three years. Digital payroll tools must be capable of generating these detailed summaries for inspection by the Department of Labor and Industries. (Source: Revised Code of Washington, RCW 49.46.070)
Digital payroll systems used for public works must be capable of generating 'Statement of Intent to Pay Prevailing Wages' and 'Affidavit of Wages Paid' filings. Software must track specific labor classifications to comply with the hourly minimum wage rate for the locality. (Source: Revised Code of Washington, RCW 39.12.040)
To set up job costing in QuickBooks: (1) Enable class and job tracking in Preferences, (2) Create a construction-specific Chart of Accounts with cost categories (labor, materials, subcontractors, equipment, overhead), (3) Set up each project as a Customer:Job, (4) Assign all income and expenses to the correct job and cost code. This allows you to track profitability at the project level. (Source: Intuit QuickBooks Help, Job Costing Setup)
The IRS requires that accounting and payroll software provide employees the option to consent to electronic delivery and that the digital format includes all required data fields found on the paper version. Employers must also provide a physical copy if the employee does not consent. (Source: 26 CFR, 31.6051-1)
QuickBooks Desktop Contractor edition supports progress invoicing natively, which can be adapted for AIA-style billing. However, for full AIA G702/G703 compliance, many contractors use add-on software like Knowify or dedicated construction management platforms that integrate with QuickBooks. (Source: Intuit QuickBooks, Progress Invoicing)
QuickBooks can be configured for PCM by creating 'Items' that map to specific COGS and Revenue accounts, allowing for the tracking of estimated vs. actual costs. This setup supports the IRS requirement for long-term contracts where the percentage of completion is used to determine gross income. (Source: 26 USC (IRS Code), 460)
Xactimate is an estimating and claims management software widely used in insurance restoration and remodeling. It generates detailed line-item estimates that feed into job costing and billing. Bookkeepers use Xactimate data to reconcile estimated vs. actual costs, process supplements, and track project profitability. (Source: Verisk Xactware, Xactimate Overview)
The American Institute of Architects (AIA) provides the G702 and G703 forms, which are the standard for progress billings. Software tools used for construction billing often integrate these templates to ensure compliance with contractual requirements for 'Application and Certificate for Payment.' (Source: AIA Contract Documents, G702-1992)
Drip Jobs is a CRM and project management platform designed for home service contractors. It tracks leads, estimates, and jobs, and can integrate with QuickBooks to sync invoices and payments. Bookkeepers use the data to reconcile revenue, track job costs, and ensure all invoiced work is recorded in the accounting system. (Source: Drip Jobs, Platform Features)
Software should facilitate the tracking of conditional and unconditional lien waivers to ensure that rights to claim a lien are properly managed upon payment. In Washington, a lien right may not be waived in advance of the time the work is performed. (Source: Revised Code of Washington, RCW 60.04.021)
Procore integrates with QuickBooks Desktop, QuickBooks Online, Sage 100 Contractor, Sage 300 CRE, and Viewpoint Vista. These integrations sync commitments, invoices, change orders, and budgets between the project management and accounting systems, reducing manual data entry and improving accuracy. (Source: Procore Technologies, Accounting Integrations)
Under OSHA standards, employers must maintain logs of work-related injuries and illnesses (Form 300). Digital project management tools used for safety tracking must meet the specific recording criteria for recordable injuries and be accessible for five years. (Source: 29 CFR, 1904.33)
Most construction companies with over $29 million in average annual gross receipts are required to use the accrual method under the Tax Cuts and Jobs Act (IRC Β§460). Smaller contractors may use cash basis, but accrual accounting with percentage-of-completion provides more accurate financial reporting for bonding, lending, and project management. (Source: IRS, IRC Β§460; TCJA 2017)
Create a fixed asset account for each major piece of equipment, and set up sub-accounts for depreciation, maintenance, fuel, and insurance. Use class tracking to allocate equipment costs to specific jobs. For hourly equipment charges, create service items with internal rates and assign them to jobs on timesheets or journal entries. (Source: Intuit QuickBooks Help, Fixed Assets)
Sage 100 Contractor offers advanced 'work-in-progress' (WIP) reporting and committed cost tracking which are essential for large-scale federal projects. QuickBooks often requires 3rd-party integrations to reach the level of detail required for federal cost-plus contracts. (Source: FASB Accounting Standards Codification (ASC), 910)
Software must be able to generate Form WH-347, which includes the name, address, and social security number of each worker, along with their classification and hourly rates of pay. The contractor must submit these weekly to the contracting agency. (Source: 29 CFR, 5.5)
If an app is used to track travel time, it must accurately reflect hours worked 'from the time the employee is required to report to the first job site.' Digital tools must clearly distinguish between commute time and compensable travel time. (Source: Washington Administrative Code, WAC 296-126-002)
The IRS allows for the storage of digital receipts as long as the electronic imaging system provides a complete and accurate image of the original and can be easily accessed. The software must preserve the details of the amount, date, place, and business purpose. (Source: IRS Revenue Procedure, 97-22)
On public works projects in Washington, software must track the 5% retainage that is withheld by the public body to serve as a trust fund for the protection of laborers and suppliers. The system must account for this as an asset until its release. (Source: Revised Code of Washington, RCW 60.28.011)
QuickBooks Online Advanced suits contractors under $3M with simpler jobsβit offers cloud access and Projects tracking. Desktop Premier/Enterprise is better for $3M+ companies needing complex multi-phase job costing, built-in progress invoicing, and certified payroll integration.
While the IRS does not mandate specific software brands, small construction contractors should use robust systems like QuickBooks or Sage that support the accrual method or the percentage-of-completion method (PCM) to accurately report gross income and costs over time. (Source: 26 CFR Β§ 1.460-4)
Accounting systems for WA contractors must be configured to separate revenue by activity typeβsuch as Retailing, Wholesaling, and Service and Other Activitiesβto ensure accurate Business and Occupation (B&O) tax reporting and compliance with state excise tax laws. (Source: WAC 458-20-170)
Software must be configured to collect and track retail sales tax on the full contract price for 'retail construction' projects, and these records must be maintained for five years to meet state audit requirements. (Source: RCW 82.32.070)
Tax Compliance & Filing
Prime contractors performing 'retail construction' services for consumers are generally taxed under the Retailing B&O tax classification. This includes constructing, repairing, or improving real property for a consumer. (Source: Revised Code of Washington, RCW 82.04.050)
Subcontractors performing work for other contractors (who then resell those services to a final consumer) are taxed under the Wholesaling B&O tax classification. To qualify, the subcontractor must obtain a valid reseller permit from the prime contractor. (Source: Revised Code of Washington, RCW 82.04.060)
A business must file Form 1099-NEC if they paid an unincorporated subcontractor $600 or more for services rendered during the tax year. This form must generally be provided to the recipient and the IRS by January 31st. (Source: Internal Revenue Code, 26 USC Β§ 6041A)
Retail contractors generally do not pay sales tax to vendors on materials that become part of the finished structure; instead, they use a reseller permit and charge the end customer sales tax on the total contract price. However, the contractor must pay sales or use tax on tools and supplies not incorporated into the project. (Source: Washington Administrative Code, WAC 458-20-170)
Any person or entity that offers to undertake, submits a bid, or performs any construction work must register with the Department of Labor & Industries. This includes general contractors and specialty contractors, and failure to register can lead to substantial fines and loss of lien rights. (Source: Revised Code of Washington, RCW 18.27.020)
General contractors must provide a $12,000 surety bond, while specialty contractors must provide a $6,000 bond; both must also carry general liability insurance of at least $250,000 for public liability and property damage. These financial protections are mandatory for maintaining an active license. (Source: Revised Code of Washington, RCW 18.27.040)
Under Section 179, construction businesses can elect to deduct the full purchase price of qualifying equipment, such as heavy machinery or vehicles, up to specific annual limits. The equipment must be placed in service during the tax year the deduction is claimed. (Source: Internal Revenue Code, 26 USC Β§ 179)
Bonus depreciation allows businesses to immediately deduct a percentage of the cost of eligible property with a recovery period of 20 years or less. For property placed in service after 2022, the allowable percentage begins to phase down annually. (Source: Internal Revenue Code, 26 USC Β§ 168(k))
If a construction business owner expects to owe $1,000 or more in federal tax for the year, they are generally required to make quarterly estimated tax payments. These payments cover income tax and self-employment tax obligations. (Source: IRS Publication 505, Tax Withholding and Estimated Tax)
Contractors are generally subject to 'nexus' rules, meaning they must pay income or gross receipts tax in any state where they have a physical presence or perform work. This often requires apportioning income between Washington and the other states involved. (Source: Washington Administrative Code, WAC 458-20-19401)
Public Road Construction involves building or repairing roads owned by the federal government or municipal corporations, and it is taxed under the Public Road Construction B&O classification. Unlike retail construction, the contractor is the consumer of all materials and must pay sales or use tax on them. (Source: Washington Administrative Code, WAC 458-20-171)
If a contractor acquires equipment outside of Washington without paying sales tax and brings it into the state for use, they must pay use tax based on the value of the article at the time of first use in Washington. (Source: Revised Code of Washington, RCW 82.12.020)
If a subcontractor fails to provide a valid Taxpayer Identification Number (TIN), the paying contractor must withhold federal income tax at the current backup withholding rate from the subcontractor's payment. (Source: Internal Revenue Code, 26 USC Β§ 3406)
Speculative builders, who perform construction on land they own, are not subject to B&O tax on the value of the construction but must pay sales or use tax on all materials and subcontractor labor. The eventual sale of the real estate is subject to Real Estate Excise Tax (REET) rather than B&O tax. (Source: Washington Administrative Code, WAC 458-20-170(2)(a))
The de minimis safe harbor allows contractors to expense items costing $2,500 or less per invoice (or $5,000 with an applicable financial statement) rather than capitalizing them. This applies to tools, small equipment, and supplies commonly purchased on construction projects.
Mobilization costsβmoving equipment, setting up temporary facilities, and initial site preparationβare generally capitalized as part of the project cost under IRC Β§263A uniform capitalization rules. They cannot be immediately deducted as current expenses.
Warranty reserves are not deductible when accrued under the all-events test. Contractors can only deduct warranty costs when they are actually incurred (paid or become fixed and determinable), per the economic performance requirement of IRC Β§461(h).
The completed contract method (CCM) defers all income and expenses until the contract is complete, while percentage-of-completion (PCM) recognizes income proportionally as work progresses. Contractors with average annual gross receipts under $29 million (2024) may elect CCM for contracts expected to be completed within 2 years.
For tax year 2024, contractors can deduct up to $1,220,000 of qualifying equipment under Section 179. The deduction phases out dollar-for-dollar when total equipment purchases exceed $3,050,000. Qualifying property includes tangible personal property like excavators, trucks, and tools used in the trade.
Construction companies generally do not need to file Form 8027, as it applies to large food and beverage establishments. However, if a contractor operates a commissary or food service facility for workers that meets the threshold (more than 10 employees on a typical business day), filing may be required.
Bid and proposal costs for construction contracts are generally deductible as ordinary and necessary business expenses under IRC Β§162. If the bid is successful, some costs may need to be capitalized as part of the contract cost under the uniform capitalization rules of IRC Β§263A.
Contractors using the percentage-of-completion method for contracts exceeding 2 years must file Form 8697 to compute look-back interest. This compares estimated income reported each year to actual income at contract completion and calculates interest owed to or from the IRS on any differences.
In Washington, contractors are generally considered consumers of materials they install. They must pay sales tax when purchasing materials (retail sales tax) or use tax if purchased out of state. The contractor does not separately charge sales tax to the customer on installed materialsβit is included in the contract price.
Yes, performance bond premiums paid by contractors are deductible as ordinary and necessary business expenses under IRC Β§162. They are considered a cost of doing business in the construction industry and can be deducted in the year paid or incurred.
Construction equipment depreciation is calculated using either the Modified Accelerated Cost Recovery System (MACRS) for tax purposes or straight-line depreciation for financial reporting. Under MACRS, most construction equipment falls under 5-year or 7-year property classes. Heavy machinery like excavators and cranes typically qualifies for 5-year depreciation. Section 179 allows immediate expensing up to $1,160,000 (2024), and bonus depreciation allows 60% first-year deduction. Consult a construction bookkeeping specialist like Scaffold Bookkeeping for optimal tax strategy. (Source: IRC Β§168, IRS Publication 946)
Construction companies can deduct: vehicle and equipment costs (Section 179 and MACRS depreciation), job materials and supplies, subcontractor payments, insurance premiums (general liability, workers comp, surety bonds), tool and equipment purchases, fuel and vehicle expenses, home office deduction for qualifying contractors, employee wages and benefits, professional services (accounting, legal), and continuing education. The key is proper documentation and job-cost allocation. Scaffold Bookkeeping helps contractors maximize deductions through proper categorization and record-keeping. (Source: IRC Β§162, IRS Publication 535)
Contractors can immediately expense up to $1,220,000 (2024 limit) in qualifying equipment placed in service before December 31, instead of depreciating it over multiple years (Source: IRC Β§179).
Most contractors benefit from an LLC taxed as an S-Corp once net income exceeds $60,000-$80,000 annually. This provides liability protection, pass-through taxation, and self-employment tax savings of $10,000-$15,000+ per year (Source: IRC Β§1366-1368).
IRS penalties scale with lateness: $60/form if 1-30 days late, $120/form if 31 days to August 1, and $310/form for intentional disregard. With 20 subcontractors, penalties can reach $6,200+ (Source: IRC Β§6721-6722).
WIP Reporting & Revenue Recognition
Under ASC 606, revenue is recognized over time if the entityβs performance creates an asset that the customer controls or if the performance creates an asset with no alternative use and the entity has an enforceable right to payment. The most common application is the input method, specifically the cost-to-cost method, which recognizes revenue based on the ratio of costs incurred to total expected costs. (Source: FASB Accounting Standards Codification, ASC 606-10-25-27)
Under ASC 606, revenue is recognized 'over time' if the contractorβs performance creates an asset that the customer controls or if the performance does not create an asset with an alternative use and there is an enforceable right to payment. This usually aligns with the Percentage-of-Completion method. (Source: FASB Accounting Standards Codification, ASC 606-10-25-27)
The cost-to-cost method is an input method that measures progress by comparing costs incurred to date against the total expected costs for the project. This ratio determines the percentage of revenue to be recognized in the current period. (Source: FASB Accounting Standards Codification, ASC 606-10-55-20)
The percentage of completion is calculated by dividing the total actual costs incurred to date by the total estimated costs at completion for the project. This percentage is then applied to the total contract price to determine the cumulative revenue earned. (Source: FASB Accounting Standards Codification, ASC 606-10-55-20)
When a contractor has earned more revenue based on progress than they have invoiced to the client, the difference is recorded as a current asset, often referred to as underbillings. (Source: FASB Accounting Standards Codification, ASC 606-10-45-1)
Washington law requires every person liable for any tax to keep and preserve, for a period of five years, suitable records as may be necessary to determine the amount of any tax for which he may be liable. For construction, this includes job cost ledgers and WIP-related documentation to support tax classifications. (Source: Revised Code of Washington, RCW 82.32.070)
Underbillings represent a contract asset where the revenue earned exceeds the amount billed to the customer. These must be reported as a current asset on the contractor's balance sheet under the 'Contract Assets' category. (Source: FASB Accounting Standards Codification, ASC 606-10-45-1)
When a contractor invoices a client for more than the revenue earned based on project progress (overbillings), the excess is recorded as a current liability or a contract liability. (Source: FASB Accounting Standards Codification, ASC 606-10-45-2)
The efforts-expended method is an input method where progress is measured based on data such as labor hours, labor dollars, or machine hours relative to the total expected inputs. (Source: FASB Accounting Standards Codification, ASC 606-10-55-17)
Overbillings represent a contract liability where the amount billed to the customer exceeds the revenue earned to date. These must be reported as a current liability on the balance sheet under the 'Contract Liabilities' category. (Source: FASB Accounting Standards Codification, ASC 606-10-45-2)
Surety companies utilize WIP schedules to evaluate a contractor's 'over/under' billing trends and job fade, which are indicators of financial health and management accuracy. This helps determine the contractor's remaining aggregate bonding capacity and overall creditworthiness. (Source: AIA Document A312-2010 Commentary, Performance Bond)
For Washington State B&O tax, contractors generally report based on the cash or accrual method consistently with their federal reporting; however, public works contracts have specific requirements for reporting retained percentages. (Source: Washington Administrative Code, WAC 458-20-197)
Under the Internal Revenue Code, most long-term contracts must be reported using the percentage of completion method, where the percentage is determined by comparing total cumulative costs incurred to the total estimated costs. Small contractors meeting specific gross receipts tests may be exempt. (Source: 26 USC (IRC), Section 460(b))
Sureties analyze the WIP schedule to monitor 'fade' (profit erosion) and to ensure the contractor has sufficient working capital to support the current and projected backlog of work. (Source: American Institute of Architects, AIA Document G703-1992)
Washington requires taxpayers to report based on their method of accounting; however, for the 'retailing' and 'wholesaling' classifications common in construction, tax is generally measured by the gross proceeds of sales. Specific adjustments are made for 'advances and reimbursements.' (Source: Washington Administrative Code, WAC 458-20-197)
A GAAP-compliant WIP schedule must include the total contract price, total estimated costs, costs incurred to date, billings to date, and the calculated earned revenue. (Source: FASB Accounting Standards Codification, ASC 606-10-50)
If it is determined that the total estimated costs on a contract will exceed the total contract revenue, the entire expected loss must be recognized in the period it becomes evident. (Source: FASB Accounting Standards Codification, ASC 605-35-25-46)
Costs that do not contribute to the entity's progress in transferring control of goods or services, such as materials delivered but not yet installed, should be excluded from the measurement of progress in the cost-to-cost method to avoid overstating revenue. (Source: FASB Accounting Standards Codification, ASC 606-10-55-21)
A long-term contract is defined as any contract for the manufacture, building, installation, or construction of property if such contract is not completed within the taxable year in which such contract is entered into. (Source: 26 USC (IRC), Section 460(f))
For federal income tax purposes, large construction companies (those exceeding the gross receipts test) are generally required to use the Section 460 Percentage of Completion Method for long-term contracts. (Source: Internal Revenue Code, 26 USC Β§ 460)
Profit fade occurs when the estimated gross profit on a job decreases as the project nears completion. Consistent fading suggests poor estimating or project management and may lead sureties to reduce bonding capacity or banks to restrict credit. (Source: AIA Document A101-2017 exhibit A, Financial Disclosures)
If uninstalled materials are significant and the customer is not yet in control, the cost should be excluded from the measurement of progress to avoid overstating revenue. (Source: FASB Accounting Standards Codification, ASC 606-10-55-21)
Retainage is generally included in the measurement of the gross contract price at the time the right to receive the retainage becomes fixed, typically upon completion and acceptance. (Source: Revised Code of Washington, RCW 82.04.080)
Contract retainage is part of the total contract price and must be accounted for even if payment is deferred. In Washington, public works retainage must be held in a trust fund; for tax purposes, it is recognized when the right to receive the funds becomes fixed. (Source: Revised Code of Washington, RCW 60.28.011)
The look-back rule requires contractors to pay or receive interest if the actual profit on a completed contract differs from the estimates used during the progress recognition phases. (Source: Internal Revenue Code, 26 USC Β§ 460(b))
Costs that do not depict the transfer of goods or services to the customer, such as certain setup or mobilization costs, may need to be capitalized as contract fulfillment costs rather than used to measure progress. (Source: FASB Accounting Standards Codification, ASC 340-40-25-5)
Changes in contract price or estimated costs are accounted for as changes in accounting estimates and must be recognized in the period the change is identified using a cumulative catch-up adjustment. (Source: FASB Accounting Standards Codification, ASC 250-10-45)
Worker Classification
To be exempt from mandatory industrial insurance, a worker must be free from control or direction over the performance of the service, the service must be either outside the usual course of business or performed outside all places of business, and the worker must be customarily engaged in an independently established trade. All three criteria must be met to avoid classification as an employee. (Source: Revised Code of Washington, RCW 51.08.195)
The IRS uses a three-factor test: (1) Behavioral control β does the company direct how work is done? (2) Financial control β does the worker have unreimbursed expenses, opportunity for profit/loss, and serve multiple clients? (3) Relationship type β are there written contracts, benefits, or permanency? No single factor is decisive. (Source: IRS Publication 15-A, Employer's Supplemental Tax Guide)
In addition to the ABC test, the individual must have a principal place of business eligible for an IRS tax deduction, maintain separate sets of books/records, and have a valid contractor registration or electrical license if required by duties. Failure to meet these specific technical criteria results in an automatic employer-employee relationship for industrial insurance purposes. (Source: Revised Code of Washington, RCW 51.08.181)
Penalties include: (1) Back payment of employment taxes (FICA, FUTA) plus interest, (2) 100% of employee FICA share the company should have withheld, (3) Failure-to-file penalties of $50-$260 per W-2 not issued, (4) Potential criminal prosecution for willful misclassification. States may impose additional penalties including back workers' comp premiums. (Source: IRS, IRC Β§3509; DOL Fact Sheet 13)
The IRS evaluates the degree of control via three categories: Behavioral (does the company control how the worker does the job), Financial (are business aspects controlled by the payer), and Type of Relationship (written contracts or employee-type benefits). The traditional 20-factor test expanded on these to include training, integration, and the right to discharge. (Source: IRS Revenue Ruling 87-41, 1987-1 C.B. 296)
Yes. Washington uses a six-part independent contractor test under RCW 51.08.195 for workers' compensation and RCW 51.08.180 for industrial insurance. The test requires that the worker is free from direction and control, is customarily engaged in an independent business, and meets specific registration, licensing, and insurance requirements. (Source: WA State L&I, RCW 51.08.195)
Under the Employee Fair Classification Act, construction employers who misclassify workers may face a civil penalty of up to $5,000 for the first violation and up to $10,000 for repeat violations. This is in addition to being liable for unpaid premiums and interest to the Department of Labor & Industries. (Source: Revised Code of Washington, RCW 49.30.010)
No, a written contract stating a worker is an independent contractor is not sufficient proof. Classification is based on the actual facts of the working relationship, specifically the degree of control exercised and whether the worker meets statutory tests like the ABC test. (Source: Washington Administrative Code, WAC 296-17-31004)
Working exclusively for one company is a strong indicator of employee status under IRS guidelines. However, it is not automatically disqualifying β the IRS considers the totality of circumstances across behavioral, financial, and relationship factors. Contractors should ensure they meet all criteria of the independent contractor test. (Source: IRS Publication 15-A)
Employers must file a Form W-2 for employees to report wages and withheld taxes. For independent contractors paid $600 or more in a year for services, the payer must file Form 1099-NEC and obtain a completed Form W-9 from the contractor. (Source: Internal Revenue Code, 26 USC Β§ 6041A)
Form SS-8 (Determination of Worker Status for Purposes of Federal Employment Taxes and Income Tax Withholding) is filed with the IRS to request an official ruling on whether a worker is an employee or independent contractor. Either party can file it. Processing typically takes at least 6 months. (Source: IRS Form SS-8 Instructions)
Maintain: (1) Written independent contractor agreements specifying scope, payment terms, and no-control clauses, (2) Proof of contractor's business registration, license, and insurance, (3) Invoices from the contractor (not timesheets), (4) Evidence the contractor serves other clients, (5) Copies of W-9 forms and 1099-NEC filings. (Source: IRS Publication 1779, Independent Contractor or Employee)
If an employer willfully misclassifies an employee as an independent contractor, they can be held liable for 100% of both the employer and employee shares of FICA taxes and federal income tax withholding. Further, Section 3509 penalties apply where there is no reasonable basis for the classification. (Source: Internal Revenue Code, 26 USC Β§ 3509)
Under US Department of Labor standards, workers who are supervised, perform manual labor, and do not share in the profits or losses of the business are generally employees. If the payer directs the sequence of work and provides tools, they are typically employees under the Fair Labor Standards Act. (Source: 29 CFR Part 795, Β§ 795.110)
A construction contractor must be registered with the Washington State Department of Labor & Industries. To qualify as an independent contractor relative to another firm, they must possess a current, valid Unified Business Identifier (UBI) number and a contractor registration that matches their business name. (Source: Revised Code of Washington, RCW 18.27.020)
Yes, in Washington construction, prime contractors can be held secondarily liable for the unpaid workers' compensation premiums of their subcontractors. To avoid this, primes must ensure subcontractors are properly registered and maintain their own records of hours worked. (Source: Revised Code of Washington, RCW 51.12.070)
The DOL uses an economic reality test to determine if a worker is economically dependent on the employer or is in business for themselves. Key factors include the opportunity for profit or loss, investment in equipment, permanency of the relationship, and the degree of skill required. (Source: US DOL Final Rule, 29 CFR Β§ 795.105)
Employers must maintain records for at least three years for all workers, including independent contractors. For contractors, these records include their UBI number, contractor registration number, and documentation proving they meet the seven-point test under RCW 51.08.195. (Source: Washington Administrative Code, WAC 296-17-35201)
Section 530 of the Revenue Act of 1978 provides relief from federal employment tax obligations if an employer consistently treated workers as contractors, had a reasonable basis for doing so (such as industry practice), and filed all required tax returns (1099s). (Source: Public Law 95-600, Section 530)
Under Washington law, a worker in the construction industry is considered an employee unless they meet all three prongs of the ABC test: (A) They are free from control or direction over the performance of the service; (B) The service is either outside the usual course of business for which the service is performed or performed outside of all the places of business of the enterprise; and (C) The individual is customarily engaged in an independently established trade, occupation, profession, or business. (Source: RCW 50.04.145)
The IRS looks at the relationship between the worker and the business by evaluating evidence of control in three categories: Behavioral Control (whether the business directs how the work is done), Financial Control (whether the business directs the financial aspects of the worker's job), and the Type of Relationship (written contracts or employee-type benefits). If the business has the right to control the details of how the services are performed, the worker is a W-2 employee. (Source: IRS Publication 15-A, Section 2)
Employers in Washington who misclassify employees as independent contractors to avoid coverage under the Industrial Insurance Act may face a penalty of up to $1,000 for each misclassified worker for a first-time offense, and up to $10,000 for subsequent offenses. (Source: RCW 51.48.025, Section 1)
Still have questions?
Our construction finance specialists are here to help with your specific situation.
Schedule a Free Consultation